astronautix.com | Saturn V |
![]() |
Saturn V 1 - Credit: NASA. 25,339 bytes. 376 x 473 pixels. |
Lunar landing booster. Design frozen before landing mode selected; could be used for either EOR or LOR methods. Ended up with same payload capability as Nova. Size dictated by ceiling height at Michoud factory selected for first stage manufacture.
Launches: 15. Failures: 0. Success Rate: 100.00% pct. First Launch Date: 05 May 1967. Last Launch Date: 14 May 1973. LEO Payload: 118,000 kg. to: 185 km Orbit. at: 28.0 degrees. Payload: 47,000 kg. to a: Translunar trajectory. Liftoff Thrust: 3,440,310 kgf. Total Mass: 3,038,500 kg. Core Diameter: 10.1 m. Total Length: 102.0 m. Development Cost $: 7,439.60 million. in 1966 average dollars. Launch Price $: 431.00 million. in 1967 price dollars.
Research on 1-million-pound thrust plus engine begun at Rocketdyne, the feasibility of which was established in March 1955.
The feasibility of a million-pound-thrust liquid-fueled rocket engine established by the Rocketdyne Division of North American Aviation, Inc.
First U.S.-built complete liquid-rocket engine having a thrust in excess of 400,000 pounds was fired for the first time at Santa Susana, Calif.
Rocket test stand capable of testing engines to 1 million pounds thrust activated at Edwards AFB, which became operational in March 1957.
The U.S. Air Force contracted with NAA, Rocketdyne Division, for preliminary design of a single-chamber, kerosene and liquid-oxygen rocket engine capable of 1 to 1.5 million pounds of thrust. During the last week in July, Rocketdyne was awarded the contract to develop this engine, designated the F-1.
Rocketdyne Division of North American announced an Air Force contract for a 1-million-pound thrust engine.
NASA requested DX priority for 1.5-million-pound-thrust F-1 engine project and Project Mercury.
NASA awarded contract to Rocketdyne of North American to build single-chamber 1.5-million-pound-thrust rocket engine.
Rocketdyne demonstrated 1-million-pound-thrust liquid-propellant rocket combustion chamber at full power.
NASA signed a definitive contract with Rocketdyne Division, NAA, for $102 million covering the design and development of a single-chamber, liquid-propellant rocket engine in the 1- to l.5-million-pound-thrust class (the F-1, to be used in the Nova superbooster concept). NASA had announced the selection of Rocketdyne on December 12.
The thrust chamber of the F-1 engine was successfully static-fired at the Santa Susana Air Force-Rocketdyne Propulsion Laboratory in California. More than one million pounds of thrust were produced, the greatest amount attained to that time in the United States.
Members of the Research Steering Committee determined the study and research areas which would require emphasis for manned flight to and from the moon and for intermediate flight steps: Additional Details: Study and research areas for manned flight to and from the moon.
The Advanced Research Projects Agency (ARPA) directed the Army Ordnance Missile Command to proceed with the static firing of the first Saturn vehicle, the test booster SA-T, in early calendar year 1960 in accordance with the $70 million program and not to accelerate for a January 1960 firing. ARPA asked to be informed of the scheduled firing date.
While awaiting the formal transfer of the Saturn program, NASA formed a study group to recommend upper-stage configurations. Membership was to include the DOD Director of Defense Research and Engineering and personnel from NASA, Advanced Research Projects Agency, Army Ballistic Missile Agency, and the Air Force. This group was later known both as the Saturn Vehicle Team and the Silverstein Committee (for Abe Silverstein, Chairman).
NASA accepted the recommendations of the Saturn Vehicle Evaluation Committee Silverstein Committee on the Saturn C-1 configuration and on a long-range Saturn program. A research and development plan of ten vehicles was approved. The C-1 configuration would include the S-1 stage (eight H-1 engines clustered, producing 1.5 million pounds of thrust), the S-IV stage (four engines producing 80,000 pounds of thrust), and the S-V stage two engines producing 40,000 pounds of thrust.
President Dwight D. Eisenhower directed NASA Administrator T. Keith Glennan "to make a study, to be completed at the earliest date practicable, of the possible need for additional funds for the balance of FY 1960 and for FY 1961 to accelerate the super booster program for which your agency recently was given technical and management responsibility."
Study issued by Huntsville of lunar landing alternatives using Saturn systems. Huntsville transferred from Army to NASA. Vought study on modular approach to lunar landing. Internally NASA decides on lunar landing as next objective after Mercury.
NASA selected Rocketdyne Division of NAA to develop the J-2, a 200,000-pound-thrust rocket engine, burning liquid hydrogen and liquid oxygen. (A decision was later made to use the J-2 in the upper stages of the Saturn C-5.)
H. Kurt Strass of STG and John H. Disher of NASA Headquarters proposed that boilerplate Apollo spacecraft be used in some of the forthcoming Saturn C-1 hunches. (Boilerplates are research and development vehicles which simulate production spacecraft in size, shape, structure, mass, and center of gravity.) These flight tests would provide needed experience with Apollo systems and utilize the Saturn boosters effectively. Four or five such tests were projected. On October 5, agreement was reached between members of Marshall Space Flight Center and STG on tentative Saturn vehicle assignments and flight plans.
The House Committee on Science and Astronautics declared: "A high priority program should be undertaken to place a manned expedition on the moon in this decade. A firm plan with this goal in view should be drawn up and submitted to the Congress by NASA. Such a plan, however, should be completely integrated with other goals, to minimize total costs. The modular concept deserves close study. Particular attention should be paid immediately to long lead-time phases of such a program." The Committee also recommended that development of the F-1 engine be expedited in expectation of the Nova launch vehicle, that there be more research on nuclear engines and less conventional engines before freezing the Nova concept, and that the Orion project be turned over to NASA. It was the view of the Committee that "NASA's 10-year program is a good program, as far as it goes, but it does not go far enough. Furthermore the space program is not being pushed with sufficient energy."
A NASA contract for approximately $44 million was signed by Rocketdyne Division of NAA for the development of the J-2 engine.
Members of STG visited the Marshall Space Flight Center to discuss possible Saturn and Apollo guidance integration and potential utilization of Apollo onboard propulsion to provide a reserve capability. Agreement was reached on tentative Saturn vehicle assignments on abort study and lunar entry simulation; on the use of the Saturn guidance system; and on future preparations of tentative flight plans for Saturns SA-6, 8, 9, and 10.
Rocketdyne Division's first static test of a prototype thrust chamber for the F-1 engine achieved a thrust of 1.550 million pounds in a few seconds at Edwards Air Force Base, Calif.
The Marshall Space Flight Center announced that 1.640 million pounds of thrust was achieved in a static- firing of the F-1 engine thrust chamber at Edwards Air Force Base, Calif. This was a record thrust for a single chamber.
NASA Associate Administrator Robert C. Seamans, Jr., established the permanent Saturn Program Requirements Committee. Members were William A. Fleming, Chairman; John L. Sloop, Deputy Chairman; Richard B. Canright; John H. Disher; Eldon W. Hall; A. M. Mayo; and Addison M. Rothrock, all of NASA Headquarters. The Committee would review on a continuing basis the mission planning for the utilization of the Saturn and correlate such planning with the Saturn development and procurement plans.
![]() | Saturn V Credit: © Mark Wade. 6,625 bytes. 185 x 893 pixels. |
The NASA Administrator and the Secretary of Defense concluded an agreement to study development of large launch vehicles for the national space program. For this purpose, the DOD-NASA Large Launch Vehicle Planning Group was created, reporting to the Associate Administrator of NASA and to the Assistant Secretary of Defense (Deputy Director of Defense Research and Engineering).
NASA announced that a complete F-1 engine had begun a series of static test firings at Edwards Rocket Test Center, Calif.
The Large Launch Vehicle Planning Group, established on July 7, 1961, began its formal existence with seven DOD and seven NASA members and alternates. Additional Details: Large Launch Vehicle Planning Group.
Phase I of a joint NASA-DOD report on facilities and resources required at launch sites to support the manned lunar landing program was submitted to Associate Administrator Robert C. Seamans, Jr., by Kurt H. Debus, Director, Launch Operations Directorate, and Maj. Gen. Leighton I. Davis, Commander of the Air Force Missile Test Center. The report, requested by Seamans on June 23, was based on the use of Nova- class launch vehicles for the manned lunar landing in a direct ascent mode, with the Saturn C-3 in supporting missions. Eight launch sites were considered: Cape Canaveral (on-shore); Cape Canaveral (off- shore); Mayaguana Island (Atlantic Missile Range downrange); Cumberland Island, Ga.; Brownsville, Tex.; White Sands Missile Range, N. Mex.; Christmas Island, Pacific Ocean; and South Point, Hawaii. On the basis of minimum cost and use of existing national resources, and taking into consideration the stringent time schedule, White Sands Missile Range and Cape Canaveral (on-shore) were favored. White Sands presented serious limitations on launch azimuths because of first-stage impact hazards on populated areas.
NASA headquarters announced that it was making a world-wide study of possible launching sites for Moon vehicles; the size, power, noise, and possible hazards of Saturn-Nova type rockets requiring greater isolation for public safety than presently available.
The Large Launch Vehicle Planning Group (Golovin Committee) notified the Marshal! Space Flight Center (MSFC), Langley Research Center, and the Jet Propulsion Laboratory (JPL) that the Group was planning to undertake a comparative evaluation of three types of rendezvous operations and direct flight for manned lunar landing. Rendezvous methods were earth orbit, lunar orbit, and lunar surface. MSFC was requested to study earth orbit rendezvous, Langley to study lunar orbit rendezvous, and JPL to study lunar surface rendezvous. The NASA Office of Launch Vehicle Programs would provide similar information on direct ascent. Additional Details: Golovin Committee evaluates three rendezvous methods for manned lunar landing.
After considering Cape Canaveral, Cape Canaveral-Merritt Island, Mayaguana-Bahamas, Cumberland-Georgia, Brownville-Texas, Christmas Island, Hawaii, and White Sands, Merritt Island selected as launch site for manned lunar flights and other missions requiring Saturn and Nova class vehicles. Based upon national space goals announced by the President in May, NASA plans called for acquisition of 80,000 acres north and west of AFMTC, to be administered by the USAF as agent for NASA and as a part of the Atlantic Missile Range. Additional Details: Merritt Island selected for Saturn V launch site..
Authorization for NASA to acquire necessary land for additional launch facilities at Cape Canaveral was approved by the Senate.
NASA announced that the government-owned Michoud Ordnance Plant near New Orleans, La., would be the site for fabrication and assembly of the Saturn C-3 first stage as well as larger vehicles. Finalists were two government-owned plants in St. Louis and New Orleans. The height of the factory roof at Michoud meant that an 8 x F-1 engined vehicle could not be built; 4 or 5 engines would have to be the maximum.
NASA selected NAA to develop the second stage (S-II) for the advanced Saturn launch vehicle. The cost, including development of at least ten vehicles, would total about $140 million. The S-II configuration provided for four J-2 liquid-oxygen - liquid-hydrogen engines, each delivering 200,000 pounds of thrust.
NASA invited 36 companies to bid on a contract to produce the first stage of the advanced Saturn launch vehicle. Representatives of interested companies would attend a pre-proposal conference in New Orleans, La., on September 26. Bids were to be submitted by October 16 and NASA would then select the contractor, probably in November.
Dr. George N. Constan of Marshall Space Flight Center named as acting manager of the new NASA Saturn fabrication plant near New Orleans by Director von Braun of Marshall Space Flight Center.
NASA bidders conference on a contract to produce the booster (S-I) stage of the Saturn vehicle was held at the Municipal Auditorium, New Orleans.
The MSFC-STG Space Vehicle Board at NASA Headquarters discussed the S- IVB stage, which would be modified by the Douglas Aircraft Company to replace the six LR-115 engines with a single J-2 engine. Funds of $500,000 were allocated for this study to be completed in March 1962. Additional Details: S- IVB stage to have a single J-2 engine.
NASA selected Pearl River site in southwestern Mississippi, 35 miles from Michoud plant in New Orleans, for static test facility for Saturn and Nova-class vehicles, completed facility to operate under direction of Marshall Space Flight Center.
Marshall Space Flight Center directed NAA to redesign the advanced Saturn second stage (S-II) to incorporate five rather than four J-2 engines, to provide a million pounds of thrust.
Golovin Committe studies launch vehicles through summer, but found the issue to be completely entertwined with mode (earth-orbit, lunar-orbit, lunar-surface rendezvous or direct flight. Two factions: large solids for direct flight; all-chemical with 4 or 5 F-1's in first stage for rendezvous options. In the end Webb and McNamara ordered development of C-4 and as a backup, in case of failure of F-1 in development, build of 6.1 m+ solid rocket motors by USAF.
On a visit to Marshall Space Flight Center by MIT Instrumentation Laboratory representatives, the possibility was discussed of emergency switchover from Saturn to Apollo guidance systems as backup for launch vehicle guidance.
NASA Associate Administrator Robert C. Seamans, Jr., commented to D. Brainerd Holmes, Director, Office of Manned Space Flight, on the report of the Rosen working group on launch vehicles, which had been submitted on November 20. Seamans expressed himself as essentially in accord with the group's recommendations.
NASA announced that The Boeing Company had been selected for negotiations as a possible prime contractor for the first stage (S-IC) of the advanced Saturn hunch vehicle. The S-IC stage, powered by five F-1 engines, would be 35 feet in diameter and about 140 feet high. The $300-million contract, to run through 1966, called for the development, construction, and testing of 24 flight stages and one ground test stage. The booster would be assembled at the NASA Michoud Operations Plant near New Orleans, La., under the direction of the Marshall Space Flight Center.
NASA announced that Douglas Aircraft had been selected for negotiation of a contract to modify the Saturn S-IV stage by installing a single 200,000-pound-thrust, Rocketdyne J-2 liquid-hydrogen/liquid-oxygen engine instead of six 15,000-pound-thrust P. & W. hydrogen/oxygen engines. Known as S-IVB, this modified stage will be used in advanced Saturn configurations for manned circumlunar Apollo missions.
![]() | F-1 engine Credit: © Mark Wade. 35,250 bytes. 455 x 365 pixels. |
Rosen Committee studies in November and December indicated that the most flexible choice for Apollo was the Saturn C-4, with two required for the earth orbit rendezvous approach or one for the lunar orbit rendezvous mission, with a smaller landed payload. The panel rejected solid motors again, but Rosen himself still pushed for Nova. An extra F-1 engine was 'slid in' for insurance, resulting in the Saturn C-5 configuration. The Manned Space Flight Management Council decided at its first meeting that the Saturn C-5 launch vehicle would have a first stage configuration of five F-1 engines and a second stage configuration of five J-2 engines. The third stage would be the S-IVB with one J-2 engine. It recommended that the contractor for stage integration of the Saturn C-1 be Chrysler Corporation and that the contractor for stage integration of the Saturn C-5 be The Boeing Company. Contractor work on the Saturn C-5 should proceed immediately to provide a complete design study and a detailed development plan before letting final contracts and assigning large numbers of contractor personnel to Marshall Space Flight Center or Michoud.
NASA made public the drawings of the three-man Apollo spacecraft to be used in the lunar landing development program, On January 9, NASA announced its decision that the Saturn C-5 would be the lunar launch vehicle.
A meeting on the technical aspects of earth orbit rendezvous was held at NASA Headquarters. Representatives from various NASA offices attended: Arthur L. Rudolph, Paul J. DeFries, Fred L. Digesu, Ludie G. Richard, John W. Hardin, Jr., Ernst D. Geissler, and Wilson B. Schramm of Marshall Space Flight Center (MSFC); James T. Rose of MSC; Friedrich O. Vonbun, Joseph W. Siry, and James J. Donegan of Goddard Space Flight Center (GSFC); Douglas R. Lord, James E. O'Neill, Richard J. Hayes, Warren J. North, and Daniel D. McKee of the NASA Office of Manned Space Flight (OMSF). Joseph F. Shea, Deputy Director for Systems, OMSF, who had called the meeting, defined in general terms the goal of the meeting: to achieve agreement on the approach to be used in developing the earth orbit rendezvous technique. After two days of discussions and presentations, the Group approved conclusions and recommendations:
NASA signed a contract with The Boeing Company for indoctrination, familiarization, and planning, expected to lead to a follow-on contract for design, development, manufacture, test, and launch operations of the first stage S-IC of the Saturn C-5 launch vehicle.
The preparation of schedules based on the NASA Fiscal Year 1962 budget (including the proposed supplemental appropriation), the Fiscal Year 1963 budget as submitted to Congress, and Fiscal Year 1964 and subsequent funding was discussed at the Manned Space Flight Management Council meeting. Program assumptions as presented by Wernher von Braun, Director, Marshall Space Flight Center (MSFC), were approved for use in preparation of the schedules :
Marshall Space Flight Center's latest schedule on the Saturn C-5 called for the first launch in the last quarter of 1965 and the first manned launch in the last quarter of 1967. If the C-5 could be man-rated on the eighth research and development flight in the second quarter of 1967, the spacecraft lead time would be substantially reduced.
A small group within the MSC Apollo Spacecraft Project Office developed a preliminary program schedule for three approaches to the lunar landing mission: earth orbit rendezvous, direct ascent, and lunar orbit rendezvous. The exercise established a number of ground rules :
A meeting to review the lunar orbit rendezvous (LOR) technique as a possible mission mode for Project Apollo was held at NASA Headquarters. Representatives from various NASA offices attended: Joseph F. Shea, Eldon W. Hall, William A. Lee, Douglas R. Lord, James E. O'Neill, James Turnock, Richard J. Hayes, Richard C. Henry, and Melvyn Savage of NASA Headquarters; Friedrich O. Vonbun of Goddard Space Flight Center (GSFC); Harris M. Schurmeier of Jet Propulsion Laboratory; Arthur V. Zimmeman of Lewis Research Center; Jack Funk, Charles W. Mathews, Owen E. Maynard, and William F. Rector of MSC; Paul J. DeFries, Ernst D. Geissler, and Helmut J. Horn of Marshall Space Flight Center (MSFC); Clinton E. Brown, John C. Houbolt, and William H. Michael, Jr., of Langley Research Center; and Merrill H. Mead of Ames Research Center. Each phase of the LOR mission was discussed separately.
The launch vehicle required was a single Saturn C-5, consisting of the S-IC, S-II, and S-IVB stages. To provide a maximum launch window, a low earth parking orbit was recommended. For greater reliability, the two-stage-to-orbit technique was recommended rather than requiring reignition of the S-IVB to escape from parking orbit.
The current concepts of the Apollo command and service modules would not be altered. The lunar excursion vehicle (LEV), under intensive study in 1961, would be aft of the service module and in front of the S-IVB stage. For crew safety, an escape tower would be used during launch. Access to the LEV would be provided while the entire vehicle was on the launch pad.
Both Apollo and Saturn guidance and control systems would be operating during the launch phase. The Saturn guidance and control system in the S-IVB would be "primary" for injection into the earth parking orbit and from earth orbit to escape. Provisions for takeover of the Saturn guidance and control system should be provided in the command module. Ground tracking was necessary during launch and establishment of the parking orbit, MSFC and GSFC would study the altitude and type of low earth orbit.
The LEV would be moved in front of the command module "early" in the translunar trajectory. After the S-IVB was staged off the spacecraft following injection into the translunar trajectory, the service module would be used for midcourse corrections. Current plans were for five such corrections. If possible, a symmetric configuration along the vertical center line of the vehicle would be considered for the LEV. Ingress to the LEV from the command module should be possible during the translunar phase. The LEV would have a pressurized cabin capability during the translunar phase. A "hard dock" mechanism was considered, possibly using the support structure needed for the launch escape tower. The mechanism for relocation of the LEV to the top of the command module required further study. Two possibilities were discussed: mechanical linkage and rotating the command module by use of the attitude control system. The S-IVB could be used to stabilize the LEV during this maneuver.
The service module propulsion would be used to decelerate the spacecraft into a lunar orbit. Selection of the altitude and type of lunar orbit needed more study, although a 100-nautical-mile orbit seemed desirable for abort considerations.
The LEV would have a "point" landing (±½ mile) capability. The landing site, selected before liftoff, would previously have been examined by unmanned instrumented spacecraft. It was agreed that the LEV would have redundant guidance and control capability for each phase of the lunar maneuvers. Two types of LEV guidance and control systems were recommended for further analysis. These were an automatic system employing an inertial platform plus radio aids and a manually controlled system which could be used if the automatic system failed or as a primary system.
The service module would provide the prime propulsion for establishing the entire spacecraft in lunar orbit and for escape from the lunar orbit to earth trajectory. The LEV propulsion system was discussed and the general consensus was that this area would require further study. It was agreed that the propulsion system should have a hover capability near the lunar surface but that this requirement also needed more study.
It was recommended that two men be in the LEV, which would descend to the lunar surface, and that both men should be able to leave the LEV at the same time. It was agreed that the LEV should have a pressurized cabin which would have the capability for one week's operation, even though a normal LOR mission would be 24 hours. The question of lunar stay time was discussed and it was agreed that Langley should continue to analyze the situation. Requirements for sterilization procedures were discussed and referred for further study. The time for lunar landing was not resolved.
In the discussion of rendezvous requirements, it was agreed that two systems be studied, one automatic and one providing for a degree of manual capability. A line of sight between the LEV and the orbiting spacecraft should exist before lunar takeoff. A question about hard-docking or soft-docking technique brought up the possibility of keeping the LEV attached to the spacecraft during the transearth phase. This procedure would provide some command module subsystem redundancy.
Direct link communications from earth to the LEV and from earth to the spacecraft, except when it was in the shadow of the moon, was recommended. Voice communications should be provided from the earth to the lunar surface and the possibility of television coverage would be considered.
A number of problems associated with the proposed mission plan were outlined for NASA Center investigation. Work on most of the problems was already under way and the needed information was expected to be compiled in about one month.
(This meeting, like the one held February 13-15, was part of a continuing effort to select the lunar mission mode).
![]() | S-1C details Credit: © Mark Wade. 40,371 bytes. 510 x 391 pixels. |
Milton W. Rosen, NASA Office of Manned Space Flight Director of Launch Vehicles and Propulsion, recommended that the S-IVB stage be designed specifically as the third stage of the Saturn C-5 and that the C-5 be designed specifically for the manned lunar landing using the lunar orbit rendezvous technique. The S-IVB stage would inject the spacecraft into a parking orbit and would be restarted in space to place the lunar mission payload into a translunar trajectory. Rosen also recommended that the S- IVB stage be used as a flight test vehicle to exercise the command module (CM), service module (SM), and lunar excursion module (LEM) (previously referred to as the lunar excursion vehicle (LEV)) in earth orbit missions. The Saturn C-1 vehicle, in combination with the CM, SM, LEM, and S-IVB stage, would be used on the most realistic mission simulation possible. This combination would also permit the most nearly complete operational mating of the CM, SM, LEM, and S-IVB prior to actual mission flight.
The F-1 engine was first fired at full power more than 1.5 million pounds of thrust) for 2.5 minutes at Edwards Rocket Site, Calif.
The Manned Space Flight Management Council approved the mobile launcher concept for the Saturn C-5 at Launch Complex 39, Merritt Island, Fla.
Wernher von Braun, Director, Marshall Space Flight Center, recommended to the NASA Office of Manned Space Flight that the lunar orbit rendezvous mode be adopted for the lunar landing mission. He also recommended the development of an unmanned, fully automatic, one-way Saturn C-5 logistics vehicle in support of the lunar expedition; the acceleration of the Saturn C-1B program; the development of high-energy propulsion systems as a backup for the service module and possibly the lunar excursion module; and further development of the F-1 and J-2 engines to increase thrust or specific impulse.
After an extended discussion, the Manned Space Flight Management Council unanimously decided:
MSC Director Robert R. Gilruth reported to the Manned Space Flight Management Council that the selection of the ablative material for the Apollo spacecraft heatshield would be made by September 1. The leading contender for the forebody ablative material was an epoxy resin with silica fibers for improving char strength and phenolic microballoons for reducing density.
In addition, Gilruth noted that a reevaluation of the Saturn C-1 and C-1B launch capabilities appeared to indicate that neither vehicle would be able to test the complete Apollo spacecraft configuration, including the lunar excursion module. Complete spacecraft qualification would require the use of the Saturn C-5.
Five NASA scientists, dressed in pressure suits, completed an exploratory study at Rocketdyne Division of the feasibility of repairing, replacing, maintaining, and adjusting components of the J-2 rocket while in space. The scientific team also investigated the design of special maintenance tools and the effectiveness of different pressure suits in performing maintenance work in space.
NASA awarded three contracts totaling an estimated $289 million to NAA's Rocketdyne Division for the further development and production of the F-1 and J-2 rocket engines.
Following a long controversy NASA selected Lunar Orbit Rendezvous (LOR) as the fastest, cheapest, and safest mode to accomplish the Apollo mission. LOR solved the engineering problem of how to land. The EOR or Direct Landing approaches required the Apollo crew to be on their backs during the landing and having to use television or mirrors to see the lunar surface. A lunar crasher stage approach had finally emerged as lesser of evils but raised other issues. LOR allowed a purpose-built lander with a logical helicopter-like crew station layout. Studies indicated LOR would allow landing 6-8 months earlier and cost $9.2 billion vs $ 10.6 billion for EOR or direct. Direct flight by this time would not involve Nova, but a scaled-down two-man spacecraft that could be launched by the Saturn C-5. Additional Details: Selection of LOR as Apollo Mission Mode.
NASA announced plans for an advanced Saturn launch complex to be built on 80,000 acres northwest of Cape Canaveral. The new facility, Launch Complex 39, would include a building large enough for the vertical assembly of a complete Saturn launch vehicle and Apollo spacecraft.
The Office of Systems under NASA's Office of Manned Space Flight summarized its conclusions on the selection of a lunar mission mode based on NASA and industry studies conducted in 1961 and 1962:
NASA's Office of Manned Space Flight issued Requests for Proposals for a study of the lunar "bus" and studies for payloads which could be handled by the C-1B and C-5 launch vehicles. Contract awards were expected by September 1 and completion of the studies by December 1.
NASA awarded a $141.1 million contract to the Douglas Aircraft Company for design, development, fabrication, and testing of the S-IVB stage, the third stage of the Saturn C-5 launch vehicle. The contract called for 11 S-IVB units, including three for ground tests, two for inert flight, and six for powered flight.
At a bidders' conference held at NASA Headquarters, proposals were requested from Centers and industry for two lunar logistic studies: a spacecraft "bus" concept that could be adapted for use first on the Saturn C-1B and later on the Saturn C-5 launch vehicles and a variety of payloads which could be soft-landed near manned Apollo missions. The latter study would determine how a crew's stay on the moon might be extended, how human capability for scientific investigation of the moon might be increased, and how man's mobility on the moon might be facilitated.
NAA finished structural requirements for a lunar excursion module adapter mating the 154-inch diameter service module to the 260-inch diameter S-IVB stage.
NASA announced that it had completed preliminary plans for the development of the $500-million Mississippi Test Facility. The first phase of a three-phase construction program would begin in 1962 and would include four test stands for static-firing the Saturn C-5 S-IC and S-II stages; about 20 support and service buildings would be built in the first phase. A water transportation system had been selected, calling for improvement of about 15 miles of river channel and construction of about 15 miles of canals at the facility. Additional Details: Plans for Apollo Mississippi Test Facility.
![]() | Saturn II stage Credit: © Mark Wade. 46,352 bytes. 488 x 368 pixels. |
MSC outlined a tentative Apollo flight plan:
The Apollo spacecraft weights had been apportioned within an assumed 90,000 pound limit. This weight was termed a "design allowable." A lower target weight for each module had been assigned. Achievement of the target weight would allow for increased fuel loading and therefore greater operational flexibility and mission reliability. The design allowable for the command module was 9,500 pounds; the target weight was 8,500 pounds. The service module design allowable was 11,500 pounds; the target weight was 11,000 pounds. The S-IVB adapter design allowable and target weight was 3,200 pounds. The amount of service module useful propellant was 40,300 pounds design allowable; the target weight was 37,120 pounds. The lunar excursion module design allowable was 25,500 pounds; the target weight was 24,500 pounds.
Rocketdyne Division successfully completed the first full-duration (250-seconds) static firing of the J-2 engine.
Flight missions of the Apollo spacecraft were to be numerically identified in the future according to the following scheme :
Pad aborts: PA-1, PA-2, etc.
Missions using Little Joe II launch vehicles: A-001, A-002, etc. Missions using Saturn C-1 launch vehicles: A-101, A-102, etc. Missions using Saturn C-1B launch vehicles: A-201, A-202, etc. Missions using Saturn C-5 launch vehicles: A-501, A-502, etc.
The 'A' denoted Apollo, the first digit stood for launch vehicle type or series, and the last two digits designated the order of Apollo spacecraft flights within a vehicle series.
NASA announced the signing of a contract with the Space and Information Systems Division of NAA for the development and production of the second stage (S-II) of the Saturn C-5 launch vehicle. The $319.9-million contract, under the direction of Marshall Space Flight Center, covered the production of nine live flight stages, one inert flight stage, and several ground-test units for the advanced Saturn launch vehicle. NAA had been selected on September 11, 1961, to develop the S-II.
NASA announced that the Douglas Aircraft Company had been awarded a $2.25million contract to modify the S-IVB stage for use in the Saturn C- 1B program.
The technique tentatively selected by NAA for separating the command and service modules from lower stages during an abort consisted of firing four 2000-pound-thrust posigrade rockets mounted on the service module adapter. With this technique, no retrorockets would be needed on the S-IV or S-IVB stages. Normal separation from the S-IVB would be accomplished with the service module reaction control system.
The U.S. Army Corps of Engineers, acting for NASA, awarded a $3.332 million contract to four New York architectural engineering firms to design the Vertical Assembly Building (VAB) at Cape Canaveral. The massive VAB became a space-age hangar, capable of housing four complete Saturn V launch vehicles and Apollo spacecraft where they could be assembled and checked out. The facility would be 158.5 meters (520 feet high) and would cost about $100 million to build. Subsequently, the Corps of Engineers selected Morrison-Knudson Company, Perini Corp., and Paul Hardeman, Inc., to construct tile VAB.
The first test of the Apollo main parachute system, conducted at the Naval Air Facility, El Centro, Calif., foreshadowed lengthy troubles with the landing apparatus for the spacecraft. One parachute failed to inflate fully, another disreefed prematurely, and the third disreefed and inflated only after some delay. No data reduction was possible because of poor telemetry. North American was investigating.
Addressing an Institute of Aerospace Science meeting in New York, George von Tiesenhausen, Chief of Future Studies at NASA's Launch Operations Center, stated that by 1970 the United States would need an orbiting space station to launch and repair spacecraft. The station could also serve as a manned scientific laboratory. In describing the 91-m-long, 10-m-diameter structure, von Tiesenhausen said that the station could be launched in two sections using Saturn C-5 vehicles. The sections would be joined once in orbit.
NASA announced a simplified terminology for the Saturn booster series: Saturn C-1 became "Saturn I," Saturn C-1B became "Saturn IB," and Saturn C-5 became "Saturn V."
NASA selected the Marion Power Shovel Company to design and build the crawler-transport, a device to haul the Apollo space vehicle (Saturn V, complete with spacecraft and associated launch equipment) from the Vertical Assembly Building to the Merritt Island, Fla., launch pad, a distance of about 5.6 kilometers (3.5 miles). The crawler would be 39.6 meters (130 feet) long, 35 meters (115 feet) wide, and 6 meters (20 feet) high, and would weight 2.5 million kilograms (5.5 million pounds). NASA planned to buy two crawlers at a cost of $4 to 5 million each. Formal negotiations began on February 20 and the contract was signed on March 29.
NASA announced the signing of a formal contract with The Boeing Company for the S-IC (first stage) of the Saturn V launch vehicle, the largest rocket unit under development in the United States. The $418,820,967 agreement called for the development and manufacture of one ground test and ten flight articles. Preliminary development of the S-IC, which was powered by five F-1 engines, had been in progress since December 1961 under a $50 million interim contract. Booster fabrication would take place primarily at the Michoud Operations Plant, New Orleans, La., but some advance testing would be done at MSFC and the Mississippi Test Operations facility.
The Apollo Spacecraft Mission Trajectory Sub-Panel discussed earth parking orbit requirements for the lunar mission. The maximum number of orbits was fixed by the S-IVB's 4.5-hour duration limit. Normally, translunar injection (TLI) would be made during the second orbit. The panel directed North American to investigate the trajectory that would result from injection from the third, or contingency, orbit. The contractor's study must reckon also with the effects of a contingency TLI upon the constraints of a free return trajectory and fixed lunar landing sites.
At a meeting on mechanical systems at MSC, Grumman presented a status report on the LEM landing gear design and LEM stowage height. On May 9, NASA had directed the contractor to consider a more favorable lunar surface than that described in the original Statement of Work. Accordingly, Grumman recommended an envelope of LEM S-IVB clearance of 152.4 centimeters (40 inches) for a landing gear radius of 457 centimeters (180 inches). Beyond this radius, a different gear scheme was considered more suitable but would require greater clearances. The landing gear envelope study was extended for one month to establish a stowed height of the LEM above the S-IVB for adapter design.
MSC informed MSFC that the length of the spacecraft-Saturn V adapter had been increased from 807.7 centimeters to 889 centimeters (318 inches to 350 inches). The LEM would be supported in the adapter from a fixed structure on the landing gear.
MSC Director Robert R. Gilruth reported to the MSF Management Council that the LEM landing gear design freeze was now scheduled for August 31. Grumman had originally proposed a LEM configuration with five fixed legs, but LEM changes had made this concept impractical. The weight and overall height of the LEM had increased, the center of gravity had been moved upward, the LEM stability analysis had expanded to cover a wider range of landing conditions, the cruciform descent stage had been selected, and the interpretation of the lunar model had been revised. These changes necessitated a larger gear diameter than at first proposed. This, in turn, required deployable rather than fixed legs so the larger gear could be stored in the Saturn V adapter. MSC had therefore adopted a four-legged deployable gear, which was lighter and more reliable than the five-legged configuration.
![]() | J-2 Credit: © Mark Wade. 29,661 bytes. 304 x 445 pixels. |
North American asked MSC if Grumman was designing the LEM to have a thrusting capability with the CSM attached and, if not, did NASA intend to require the additional effort by Grumman to provide this capability. North American had been proceeding on the assumption that, should the service propulsion system (SPS) fail during translunar flight, the LEM would make any course corrections needed to ensure a safe return trajectory. Additional Details: Grumman to design the LEM to have a thrusting capability with the Apollo CSM attached.
At a LEM Mechanical Systems Meeting in Houston, Grumman and MSC agreed upon a preliminary configuration freeze for the LEM-adapter arrangement. The adapter would be a truncated cone, 876 centimeters (345 inches) long. The LEM would be mounted inside the adapter by means of the outrigger trusses on the spacecraft's landing gear. This configuration provided ample clearance for the spacecraft, both top and bottom (i.e., between the service propulsion engine bell and the instrument unit of the S-IVB).
At this same meeting, Grumman presented a comparison of radially and laterally folded landing gears (both of 457-centimeter (180-inch) radius). The radial-fold configuration, MSC reported, promised a weight savings of 22-2 kilograms (49 pounds). MSC approved the concept, with an 876-centimeter (345-inch) adapter. Further, an adapter of that length would accommodate a larger, lateral fold gear (508 centimeters (200 inches)), if necessary. During the next several weeks, Grumman studied a variety of gear arrangements (sizes, means of deployment, stability, and even a "bending" gear). At a subsequent LEM Mechanical Systems Meeting, on November 10, Grumman presented data (design, performance, and weight) on several other four-legged gear arrangements - a 457-centimeter (180-inch), radial fold "tripod" gear (i.e., attached to the vehicle by three struts), and 406.4-centimeter (160-inch) and 457-centimeter (180-inch) cantilevered gears. As it turned out, the 406.4-centimeter (160-inch) cantilevered gear, while still meeting requirements demanded in the work statement, in several respects was more stable than the larger tripod gear. In addition to being considerably lighter, the cantilevered design offered several added advantages:
The Guidance and Performance Sub-Panel, at its first meeting, began coordinating work at MSC and MSFC. The sub-panel outlined tasks for eac Center: MSFC would define the dispersions comprising the launch vehicle performance reserves, prepare a set of typical translunar injection errors for the Saturn V launch vehicle, and give MSC a typical Saturn V guidance computation for injection into an earth parking orbit. MSC would identify the constraints required for free-return trajectories and provide MSFC with details of the MIT guidance method. Further, the two Centers would exchange data each month showing current launch vehicle and spacecraft performance capability. (For operational vehicles, studies of other than performance capability would be based on control weights and would not reflect the current weight status.)
The first production F-1 engine for the Apollo Saturn V was flown from Rocketdyne's Canoga Park, Calif., facility, where it was manufactured, to MSFC aboard Aero Spacelines' "Pregnant Guppy."
NASA Associate Administrator for Manned Space Flight George E. Mueller notified the Directors of MSC, MSFC, and LOC that he intended to plan a flight schedule which would have a good chance of being met or exceeded. To this end, he directed that "all-up" spacecraft and launch vehicle tests be started as soon as possible; all Saturn IB flights would carry CSM and CSM LEM configurations; and two successful unmanned flights would be flown before a manned mission on either the Saturn IB or Saturn V.
On November 18, Mueller further defined the flight schedule planning. Early Saturn IB flights might not be able to include the LEM, but every effort must be made to phase the LEM into the picture as early as possible. Launch vehicle payload capability must be reached as quickly as practicable. Subsystems for the early flights should be the same as those intended for lunar missions. To conserve funds, the first Saturn V vehicle would be used to obtain reentry data early in the Saturn test program.
The Boeing Company and NASA signed a $27.4 million supplemental agreement to the contract for development, fabrication, and test of the S-IC (first) stage of the Saturn V launch vehicle.
NASA awarded a $19.2 million contract to Blount Brothers Corporation and M. M. Sundt Construction Company for the construction of Pad A, part of the Saturn V Launch Complex 39 at LOC.
NASA and contractor studies showed that, in the event of an engine hard-over failure during maximum q, a manual abort was impractical for the Saturn I and IB, and must be carried out by automatic devices. Studies were continuing to determine whether, in a similar situation, a manual abort was possible from a Saturn V.
At its Santa Susana facility, Rocketdyne conducted the first long-duration (508 seconds) test firing of a J-2 engine. In May 1962 the J-2's required firing time was increased from 250 to 500 seconds.
ASPO requested that Grumman make a layout for transmittal to MSFC showing space required in the S-IVB instrument unit for 406.4- and 457-centimeter (160- and 180-inch) cantilevered gears and for 508-centimeter (200-inch)-radius lateral fold gears.
NASA Headquarters approved a $48,064,658 supplement to the Douglas Aircraft Company, Inc., contract for 10 additional S-IVB stages, four for the Saturn IB and six for the Saturn V missions.
MSFC Director Wernher von Braun described to Apollo Spacecraft Program Manager Joseph F. Shea a possible extension of Apollo systems to permit more extensive exploration of the lunar surface. Huntsville's concept, called the Integrated Lunar Exploration System, involved a dual Saturn V mission (with rendezvous in lunar orbit) to deliver an integrated lunar taxi/shelter spacecraft to the Moon's surface. Additional Details: Extension of Apollo systems to permit more extensive exploration of the lunar surface..
MSC and MSFC officials discussed development flight tests for Apollo heatshield qualification. Engineers from the Houston group outlined desired mission profiles and the number of missions needed to qualify the component. MSFC needed this information to judge its launch vehicle development test requirements against those of MSC to qualify the heatshield. By the middle of the month, Richard D. Nelson of the Mission Planning and Analysis Division (MPAD) had summarized the profiles to be flown with the Saturn V that satisfied MSC's needs. Nelson compiled data for three trajectories that could provide reentry speeds of around 11,000 meters (36,000 feet) per second, simulating lunar return. As an example, "Trajectory 1" would use two of the booster's stages to fire into a suborbital ballistic path, and then use a third stage to accelerate to the desired reentry speed.
Flight profiles for Saturn IB missions for heatshield qualification purposes proved to be a little more difficult because "nobody would or could define the requirements or constraints, or test objectives." In other words, MSFC requirements for booster development test objectives and those of MSC for the spacecraft heatshield conflicted. So compromises had to be forged. Finally Ted H. Skopinski and other members of MPAD bundled up all of ASPO's correspondence on the subject generated from the various pertinent sources: MSFC, MSC, and contractors. From this, the Skopinski group drafted "broad term test objectives and constraints" for the first two Saturn IB flights (missions 201 and 202). Generally, these were to man-rate the launch vehicle and the CSM and to "conduct entry tests at superorbital entry velocities" (8,500 to 8,800 meters per second) (28,000 to 29,000 feet per second). Skopinski also enumerated specific test objectives covering the whole spacecraft-launch vehicle development test program. These were first distributed on March 27, and adjustments were made several times later in the year.
![]() | Saturn V No. d Credit: NASA. 15,613 bytes. 342 x 467 pixels. |
The Lockheed-California Company released details of its recommendations to MSC on a scientific space station program. The study concluded that a manned station with a crew of 24 could be orbiting the Earth in 1968. Total cost of the program including logistics spacecraft and ground support was estimated at $2.6 billion for five years' operation. Lockheed's study recommended the use of a Saturn V to launch the unmanned laboratory into orbit and then launching a manned logistics vehicle to rendezvous and dock at the station.
OMSF outlined launch vehicle development, spacecraft development, and crew performance demonstration missions, using the Saturn IB and Saturn V:
MSFC awarded Rocketdyne a definitive contract (valued at $158.4 million) for the production of 76 F-1 engines for the first stage of the Saturn V launch vehicle and for delivery of ground support equipment.
A study to recommend, define, and substantiate a logical approach for establishing a rotating manned orbital research laboratory for a Saturn V launch vehicle was made for MSC. The study was performed by the Lockheed-California Company, Burbank, California. It was based on the proposition that a large rotating space station would be one method by which the United States could maintain its position as a leader in space technology. Additional Details: Rotating manned orbital research laboratory for a Saturn V launch vehicle..
NASA selected IBM, Federal Systems Division, to develop and build the instrument units (IU) for the Saturn IB and Saturn V launch vehicles. (IBM had been chosen by NASA in October 1963 to design and build the IU data adapters and digital guidance computers and to integrate and check out the IUs.) Under this new contract, expected to be worth over $175 million, IBM would supply the structure and the environmental control system. NASA would furnish the telemetry system and the stabilized platform (ST-124M) of the guidance system. MSFC would manage the contract.
MSC's Apollo Spacecraft Program Office (ASPO) approved a plan (put forward by the MSC Advanced Spacecraft Technology Division to verify the CM's radiation shielding. Checkout of the radiation instrumentation would be made during manned earth orbital flights. The spacecraft would then be subjected to a radiation environment during the first two unmanned Saturn V flights. These missions, 501 and 502, with apogees of about 18,520 km (10,000 nm), would verify the shielding. Gamma probe verification, using spacecraft 008, would be performed in Houston during 1966. Only Block I CM's would be used in these ground and flight tests. Radiation shielding would be unaffected by the change to Block II status.
The Guidance and Control Implementation Sub-Panel of the MSC-MSFC Flight Mechanics Panel defined the guidance and control interfaces for Block I and II missions. In Block II missions the CSM's guidance system would guide the three stages of the Saturn V vehicle; it would control the S- IVB (third stage) and the CSM while in earth orbit; and it would perform the injection into a lunar trajectory. In all of this, the CSM guidance backed up the Saturn ST-124 platform. Actual sequencing was performed by the Saturn V computer.
ASPO's Operations Planning Division defined the current Apollo mission programming as envisioned by MSC. The overall Apollo flight program was described in terms of its major phases: Little Joe II flights (unmanned Little Joe II development and launch escape vehicle development); Saturn IB flights (unmanned Saturn IB and Block I CSM development, Block I CSM earth orbital operations, unmanned LEM development, and manned Block II CSM/LEM earth orbital operations); and Saturn V flights (unmanned Saturn V and Block II CSM development, manned Block II CSM/LEM earth orbital operations, and manned lunar missions).
There appeared to be some confusion and/or disagreement concerning whether one or two successful Saturn V reentry tests were required to qualify the CM heatshield. A number of documents relating to instrumentation planning for the 501 and 502 flight indicated that two successful reentries would be required. The preliminary mission requirements document indicated that only a single successful reentry trajectory would be necessary. The decision would influence the measurement range capability of some heatshield transducers and the mission planning activity being conducted by the Apollo Trajectory Support Office. The Structures and Mechanics Division had been requested to provide Systems Engineering with its recommendation.
The MSC-Marshall Space Flight Center (MSFC) Guidance and Control Implementation Sub-Panel set forth several procedural rules for translunar injection (TLI):
At its Sacramento test site, Douglas Aircraft Company static-fired a "battleship" S-IVB second stage of the Saturn IB vehicle, for 10 sec. (A battleship rocket stage was roughly the vehicle's equivalent to a boilerplate spacecraft.) On January 4, 1965, after further testing of the stage's J-2 engine, the stage underwent its first full-duration firing, 480 sec.
Douglas Aircraft Company delivered the first S-IVB stage to Marshall Space Flight Center for extensive vibration, bending, and torsional testing. The stage was not an actual flight stage and contained mockups of the engine and other components, but it duplicated the flight article in weight, mass, center of gravity, and stiffness.
At the fourth meeting of the Reference Trajectory Sub-Panel, MSC and MSFC members agreed on a trajectory with a launch azimuth of 108 degrees. Translunar injection would be performed over the Pacific Ocean during the first or second orbits. First-orbit injection would fix the minimum time required before the maneuver. Injection on the second pass would determine consequent penalties. The actions were initiated by Mission Planning and Analysis Division (MPAD) and were required to solidify and minimize analytical studies and operational planning.
MSC Deputy Director George M. Low issued a memorandum regarding differences in the Apollo schedule as made public in an Associated Press release with a Houston, Texas, dateline. Low cited the following statement by George E. Mueller, Associate Administrator for Manned Space Flight, and said it "represents our official and only position on Apollo schedules:
Significant agreements from the Eleventh MSC-MSFC Flight Mechanics, Dynamics, Guidance and Control Panel meeting were:
Apollo Program Director Samuel C. Phillips forecast "heavy ground testing" for Apollo during 1965. The coming months, he said, should see the completion of testing on the first Apollo spacecraft intended for manned space flight, as well as flight qualification of the Saturn IB and initial testing of the Saturn V launch vehicles.
![]() | Launch vehicles - Launch vehicles of the world as known in 1980 Credit: © Mark Wade. 34,549 bytes. 330 x 402 pixels. |
ASPO approved the technique for LEM S-IVB separation during manned missions, a method recommended jointly by North American and Grumman. After the CSM docked with the LEM, the necessary electrical circuit between the two spacecraft would be closed manually. Explosive charges would then free the LEM from the adapter on the S-IVB.
The first major Saturn V flight component, a 10-m (33-ft) diameter, 27,215 kg (60,000 lb corrugated tail section which would support the booster's 6,672 kilonewtons (1.5-million-lb) thrust engines, arrived at MSFC from NASA's Michoud Operations near New Orleans. The section was one of five major structural units comprising Saturn V's first stage.
Pacific Crane and Rigging Company received a NASA contract, worth $8.3 million, to install ground equipment at Kennedy Space Center's Saturn V facility, Launch Complex 39. On the following day, the Army Corps of Engineers awarded a $2,179,000 contract to R. E. Carlson Corporation, St. Petersburg, Fla., to modify Launch Complex 34 to handle the Saturn IB.
The Apollo-Saturn Crew Safety Panel decided on a number of emergency detection system (EDS) and abort procedures for the early Apollo flights:
North American completed the first ground test model of the S-II stage of the Saturn V.
ASPO Manager Joseph F. Shea clarified the manned unmanned capabilities required of Block I CSM spacecraft to ensure that end-item specifications appropriately reflect those capabilities.
CSMs 017 and 020 would fly unmanned entry tests on the Saturn V and need not be capable of manned missions. CSMs 012 and 014 were to be delivered to KSC for manned orbital missions on the Saturn IB but must be capable of being modified to fly unmanned missions.
The planning for CSM 012 should be such that the mission type could be selected 5½ months prior to the scheduled launch of the 204 mission, yet not delay the launch.
To eliminate interference between the S-IVB stage and the instrument unit, MSC directed North American to modify the deployment angle of the adapter panels. Originally designed to rotate 170 degrees, the panels should open but 45 degrees (60 degrees during abort), where they were to be secured while the CSM docked with and extracted the LEM.
But at this smaller angle, the panels now blocked the CM's four flush- mounted omnidirectional antennas, used during near-earth phases of the mission. While turning around and docking, the astronauts thus had to communicate with the ground via the steerable high gain antenna. For Block II spacecraft, therefore, MSC concurrently ordered North American to broaden the S-band equipment's capability to permit it to operate within 4,630 km (2,500 nm) of earth.
Missiles and Rockets reported a statement by Joseph F. Shea, ASPO manager, that MSC had no serious weight problems with the Apollo spacecraft. The current weight, he said, was 454 kg (1,000 lbs) under the 40,823 kg (90,000 lb) goal. Moreover, the increased payload of the Saturn V to 43,091 kg (95,000 lbs) permitted further increases. Shea admitted, however, that the LEM was growing; recent decisions in favor of safety and redundancy could raise the module's weight from 13,381 kg to 14,575 kg (29,500 lbs to 32,000 lbs).
Marshall Space Flight Center finalized a $2,697,546 addition to an existing contract with Douglas Aircraft Company to provide for environmental testing of a full-scale S-IVB forward stage simulator, a full-scale test instrument unit, and an Apollo thermal simulator. Testing would be conducted in Douglas' 11.89-m- (39-ft-) diameter space simulator at Huntington Beach, California, and would simulate a typical Saturn V flight from launch to earth orbit and injection into lunar path.
Construction workers emplaced the final beam in the structural skeleton of the Vertical Assembly Building at Merritt Island (KSC), Florida. Scheduled for completion in 1966, the cavernous structure (160 m (525 ft) tall and comprising 10,968,476 cu m (129 million cu ft)) would provide a controlled environment for assembling Saturn V launch vehicles and mating them to Apollo spacecraft.
MSFC conducted the first clustered firing of the Saturn V's first stage (the S-IC). The booster's five F-1 engines burned for about 6½ seconds and produced 33,360 kilonewtons (7.5 million lbs) thrust.
Eight days later, at its static facility in Santa Susana, California, North American first fired the S-II, intermediate stage of the Saturn V. The event was chronicled as the "second major Saturn V milestone" during April. Additional Details: First clustered firing of Saturn V's first stage.
NASA and Boeing negotiated a contract modification. For an additional $3,135,977, Boeing would furnish instrumentation equipment and engineering support for Marshall Space Flight Center's program for dynamic testing of the Saturn V.
North American's Rocketdyne Division conducted the 1,000th test firing of the Saturn V's first-stage engine, the F-1.
NASA announced negotiations with Douglas Aircraft Company for nine additional S-IVB stages to be used as the third stage of the Saturn V launch vehicle being developed at Marshall Space Flight Center. Work was to include related spares and launch support services. The S-IVB contract, presently valued at $312 million, would be increased by $150 million for the additional work.
On the basis of information from the two Apollo spacecraft manufacturers, the Systems Engineering Division (SED) reported a possible thermal problem with the Saturn V during ascent:
The Saturn V's booster, the S-IC stage, made a "perfect" full-duration static firing by burning for the programmed 2.5 minutes at its full 33,360-kilonewton (7.5-million-lbs) thrust in a test conducted at MSFC. The test model demonstrated its steering capability on command from the blockhouse after 100 sec had elapsed; the firing consumed 2.133-million liters (537,000 gallons) of kerosene and liquid oxygen.
Two Saturn milestones occurred on the same day. At Santa Susana, Calif., North American conducted the first full-duration captive firing of an S-II, second stage of the Saturn V. And at Sacramento, Douglas static-tested the first flight-model S-IVB, second stage for the Saturn IB. This latter marked the first time that a complete static test (encompassing vehicle checkout, loading, and firing) had been controlled entirely by computers.
Douglas Aircraft Company static-fired the S-IVB in a test at Sacramento, Calif., simulating the workload of a lunar mission. The stage was run for three minutes, shut down for half an hour, then reignited for almost six minutes.
![]() | N1 and Saturn V Credit: © Mark Wade. 25,611 bytes. 575 x 467 pixels. |
MSC's Flight Operations Division requested an investigation of the feasibility of performing an abort from an inoperative S-IVB booster on the AS-206 unmanned LEM mission.
To aid in defining abort limits for the emergency detection system, MSC authorized North American to determine the ultimate strength of the spacecraft based on failure trajectories of the Saturn IB and Saturn V vehicles.
John H. Disher, Saturn/Apollo Applications Deputy Director, requested the Manned Space Flight Management Operations Director to officially change the designation of the Saturn IB/Centaur Office to Saturn Applications. This change, Disher said, reflected the change in status of the office and provided for necessary management of potential Saturn Applications such as the Saturn V/Voyager by the Office of Manned Space Flight. However, on the same day, Disher ordered E. F. O'Connor at MSFC to halt all Saturn IB/Centaur efforts (except those already underway that could not be recalled) and disapproved the request for an additional $1.1 million for the program. (Any funds required for definition of a Saturn V/Voyager mission, he said, would be authorized separately.)
An 889-kilonewton (200,000-lb) thrust J-2 engine was captive-fired for 388 sec on a new test stand at MSFC. The J-2 engine would be used to power the Saturn S-IVB stage for the Saturn V. Ten tests of the liquid hydrogen-liquid oxygen powered rocket engine had been conducted at MSFC since the J-2 engine test facility was put into use in August 1965.
CSM ultimate static testing began. A failure occurred at 140 percent of the limit load test which simulated the end of the first-stage Saturn V boost. Additional Details: Apollo CSM ultimate static testing began.
The MSC Systems Development Branch rejected a proposal that the Development Flight Instrumentation (DFI) on LEM-3 be deleted for the following reasons:
Apollo Program Director Samuel C. Phillips informed J. L. Atwood, President of North American Aviation, Inc., that he and the team working with him in examining the Apollo Spacecraft and S-II stage programs had completed their task "in sufficient detail . . . to formulate reasonably accurate assessment of the current situation concerning these two programs." Phillips and a task force had started this study at North American November 22, 1965.
Phillips added: "I am definitely not satisfied with the progress and outlook of either program and am convinced that the right actions now can result in substantial improvement of position in both programs in the relatively near future.
"Inclosed are ten copies of the notes which we compiled on the basis of our visits. They include details not discussed in our briefing and are provided for your consideration and use.
"The conclusions expressed in our briefing and notes are critical. Even with due consideration of hopeful signs, I could not find a substantive basis for confidence in future performance. I believe that a task group drawn from NAA at large could rather quickly verify the substance of our conclusions, and might be useful to you in setting the course for improvements.
"The gravity of the situation compels me to ask that you let me know, by the end of January if possible, the actions you propose to take. . . ."
MSC and Grumman completed negotiations to convert the LEM contract from cost-plus-fixed-fee to cost- plus-incentive fee. In addition to schedule and performance incentives, bonus points would be awarded for cost control during FY 66 and FY 67. Four LEMs were also added to the program. LEM mockup-3 would be used as the KSC verification vehicle; LEM test article-2 and LEM test article-10 (refurbished vehicles) would be used in the first two flights of the Saturn V launch vehicle.
A total of 167 contract change authorizations (CCAs) to the Grumman contract had been issued by December 31. Negotiation of the proposal for the conversion to a cost-plus-incentive-fee included all CCAs through No. 162, and CCA amendments dated before December 9. Proposals for CCAs 163167 were in process and would be submitted according to contract change procedures.
The 500-second limitation for the Block I service propulsion system SPS engine qualification program was increased to 600 seconds for the last three altitude qualification tests. The spacecraft 020 SPS mission duty cycle required a 310-second burn and a 205-second burn. Discussions with Systems Engineering Division indicated that the long SPS burns were needed to support a full-duration S-IVB mission and there was little likelihood the requirement could be modified. The Block II engine delivery schedules prohibited obtaining a Block II engine in time to support spacecraft 020.
MSFC issued requests for proposals to the aerospace industry for definition studies of integrating experiment hardware into AAP space vehicles-i.e., payload integration in the Apollo lunar module, the Saturn instrument unit, and the S-IVB stage of the Saturn IB and Saturn V launch vehicles. Following evaluation of the proposals, MSFC would select two or more firms for negotiation of nine-month study contracts to be managed by Huntsville as the Center responsible for payload integration of this portion of AAP. (MSC was responsible for payload integration of the Apollo CSM.)
Among these would be three 'S-IVB/Spent-Stage Experiment Support Modules' (i.e., 'wet' Workshops), three Saturn V-boosted orbital laboratories, and four Apollo telescope mounts. The initial AAP launch was slated for April 1968. The schedule was predicated upon non-interference with the basic Apollo lunar landing program, minimum modifications to basic Apollo hardware, and compatibility with existing Apollo launch vehicles.
AS-500-F, the Pathfinder first full-scale Apollo Saturn V launch vehicle and spacecraft combination, was rolled out from Kennedy Space Center's Vehicle Assembly Building to the launch pad, for use in verifying launch facilities, training crews, and developing test procedures. The 111-meter, 227,000-kilogram vehicle was moved by a diesel-powered steel-link-tread crawler-transporter exactly five years after President John F. Kennedy asked the United States to commit itself to a manned lunar landing within the decade. Meanwhile, schedule for Saturn V threatened by continued problems in development of S-II stage (inability to get sustained 350-second burns without instrumentation failures, shutoffs, minor explosions).
Headquarters informed MSC that MSFC had been assigned development responsibility for the S027 X-ray Astronomy experiment for integration with the Saturn S-IVB/instrument unit. Should development be found not feasible, a modified version of the equipment was planned. MSC was requested to study:
MSC Director of Flight Crew Operations Donald K. Slayton and Director of Flight Operations Christopher C. Kraft, Jr., told ASPO Manager Joseph F. Shea: "A comprehensive examination of the Apollo missions leading to the lunar landing indicates that there is a considerable discontinuity between missions AS-205 and AS-207/208. Both missions AS-204 and AS-205 are essentially long duration system validation flights. AS-207/208 is the first of a series of very complicated missions. A valid operational requirement exists to include an optical equal-period rendezvous on AS-205. The rendezvous would be similar to the one initially planned for the Gemini VII flight using, in this case, the S-IVB as the target vehicle." The maneuver would give the crew an opportunity to examine the control dynamics, visibility, and piloting techniques required to perform the basic AS-207/208 mission.
![]() | Saturn V Credit: NASA. 22,148 bytes. 383 x 600 pixels. |
MSC requested LaRC to study the visibility of the S-IVB/SLA combination from the left-hand couch in the command module with the couch in the docked position. (Two positions could be attained, one of them a docking and rendezvous position that moved the seat into a better viewing area from the left-hand window.) LM and CM mockups were already at Langley from the CM-active moving-base docking simulation conducted May-July 1965.
The request was initiated because the flight crew had to rely on an out- the-window reference of the S-IVB/SLA to verify separation of the LM/CSM combination from the S-IVB/SLA. The question arose as to whether the out-the-window reference was sufficient or whether an electromechanical device with a panel readout in the CM was required to verify separation.
MSC requested Ames Research Center to conduct a manual control simulation of the Saturn V upper stages with displays identical to those planned in the spacecraft. On August 5, Brent Creer and Gordon Hardy of Ames had met with representatives from ASPO, Guidance and Control Division, and Flight Crew Operations Directorate to discuss implementation of a modified Ames simulation which would determine feasibility of manual control from first stage burnout, using existing spacecraft displays and control interfaces. Simulations at Ames in 1965 had indicated that the Saturn V could be manually flown into orbit within dispersions of 914 meters in altitude, and 0.1 degree in flight path angle. Additional Details: Manual control simulation of the Saturn V upper stages with Apollo.
Langley Research Center informed MSC that the Apollo Visibility Study requested by MSC would be conducted. Langley mockups could be used along with an SLA panel to be provided by MSC from Tulsa North American. The proposed study would be semistatic, with the astronaut seated in the existing CM mockup and viewing the S-IVB/SLA mockup. The positions of the mockups would be varied manually by repositioning the mockup dollies, and the astronaut would judge the separation distance and alignment attitude. The study was expected to start at the end of October or early November and last two or three weeks.
Propellant tanks of service module 017 failed during a pressure test at North American Aviation, Downey, Calif. The planned test included several pressure cycles followed by a 48-hour test of the tanks at the maximum operating pressure of 165 newtons per square centimeter (240 pounds per square inch). Normal operating pressure was 120 newtons per square centimeter (175 pounds per square inch). After 1 hour 40 minutes at 165 newtons the failure occurred.
SM 017 (designed for SA-501) had been pulled for this test after cracks had been detected in the tanks of SM 101. SM 017 had been previously proof-tested a short time (a matter of minutes) at 220 newtons per square centimeter (320 pounds per square inch).
A team was set up at North American Aviation to look into the failure and its possible impact on the Saturn IB and Saturn V Apollo missions. MSC had two observers on the team, which was to make its findings and recommendations available by November 4.
North American Aviation identified the problem as stress-corrosion cracking resulting from use of methanol as a test liquid at pressures causing above threshold stresses. No tanks subjected to methanol at high stress levels would be used. Freon and isopropyl alcohol, respectively, were recommended for test fluids in the oxidizer and fuel systems, with the stipulation that the equipment had not previously seen propellant and would receive a hot gaseous nitrogen purge after completion of the cold flow operation.
Maurice J. Raffensperger, Earth Orbital Mission Studies Director in NASA Hq, spelled out revised criteria for design of a one-year Workshop in space (criteria to be incorporated by MSFC and MSC planners into their proposed configurations). Maurice J. Raffensperger, Earth Orbital Mission Studies Director in NASA Hq, spelled out revised criteria for design of a one-year Workshop in space (criteria to be incorporated by MSFC and MSC planners into their proposed configurations): This 'interim space station' should be ready for launch in January 1971. The design had to be a minimum-cost structure capable of a two-year survival in low Earth orbit. (Raffensperger speculated that a 'dry-launched' S-IVB stage could be employed without major structural changes.) Initial vehicle subsystems were to consist of flight-qualified Apollo and Manned Orbiting Laboratory hardware capable of one-year operation. Operation of the station during the second year was to be accomplished by means of a long- duration 'developmental systems' module that would be attached to the original space station structure (and would be developed separately as part of the long-duration space station program). Initial launch of the station would be with a Saturn V (and include CSM). This interim space station must be suited for operation in either zero-g or with artificial gravity (using the 'simplest, least expensive' approach). Cost of the hardware must not exceed $200 million (excluding launch vehicle and the long-duration subsystems module). Cargo resupply and crew changes were to be carried out using Apollo Applications- modified CSMs (limited to three Saturn IBs per year).
Six months later, a LM/ATM launch would follow a second manned flight. The LM/ATM would rendezvous and dock to the cluster. The first Workshop launch was scheduled for June 1968. As opposed to the habitable OWS and cluster concept which projected a much more complex program, the S-IVB SSESM had been a comparatively simple mission requiring no rendezvous and docking and no habitation equipment. A major similarity between the old S-IVB/SSESM concept and the cluster concept was use of the S-IVB stage to put the payload into orbit before passivation and pressurization of the stage's hydrogen tanks. The new cluster concept embodied the major step of making the Saturn IVB habitable in orbit, incorporating a two-gas atmosphere (oxygen and nitrogen) and a 'shirt- sleeve' environment. The OWS would contain crew quarters in the S IVB hydrogen tank (two floors and walls installed on the ground), which would be modified by Douglas Aircraft Company under MSFC management; an airlock module (previously called the SSESM) attached to the OWS, which would be built by McDonnell Aircraft Corporation under MSC management; and a multiple docking adapter (MDA), which would contain five docking ports permitting up to five modules to be docked to the Workshop at any one time. The MDA would also house most OWS astronaut habitability equipment and many experiments. The schedule called for 22 Saturn IB and 15 Saturn V launches. Two of the Saturn IBs would be launched a day apart-one manned, the other unmanned. Flights utilizing two Saturn V Workshops and four LM ATM missions were also scheduled.
In response to a request from Apollo Program Director Samuel C. Phillips on November 21, MSC reported its evaluation of Atlantic versus Pacific Ocean prime recovery areas for all Saturn V Apollo missions. MSC said that a change of recovery area to the Atlantic for AS-501 and AS-502 would cause some schedule slip and compromise of mission objectives and would not necessarily save recovery ship effort. For AS-503 and similar nonlunar missions, adjustments could be made to the mission profile to result in a prime recovery in the Atlantic area. Secondary support would be necessary in the Pacific, however. The report stressed that confining recovery to the Atlantic area for lunar missions would severely curtail the number of launch windows available.
In a December 30 letter to MSC, KSC, and MSFC, the Apollo Program Director referred to the study and said it had been determined that plans for Pacific recovery for the AS-501 and AS-502 missions were justified.
Langley Research Center reported on its November study of visibility from the CSM during extraction of the LM from the S-IVB stage. The study had been made in support of the AS-207/208A mission, with assistance of MSC and North American Aviation personnel, to
Lewis L. McNair, MSFC Chairman of the Flight Mechanics Panel, told Calvin H. Perrine, Jr., MSC, that the Guidance and Performance Sub-Panel had been unable to reach an agreement on venting the liquid-oxygen (LOX) tank of the Saturn V S-IVB stage during earth parking orbit. McNair pointed out that MSFC did not want a programmed LOX vent and that MSC did. He added that the issue must be resolved in order to finalize the AS-501 attitude maneuver and venting timeline.
![]() | Saturn V 2 Credit: NASA. 30,251 bytes. 377 x 470 pixels. |
Apollo Program Director Samuel C. Phillips told NASA Associate Administrator for Manned Space Flight George E. Mueller that studies had been completed on the use of "direct translunar injection" (launch directly into a trajectory to the moon) as a mode of operation for lunar landing missions. The principal advantages would be potential payload increases and elimination of the S-IVB stage restart requirement. The disadvantage was that there would be no usable launch windows for about half of each year and a reduced number of windows for the remainder of the year. Phillips was confident the launch vehicle would have adequate payload capability, since Saturn V performance continued to exceed spacecraft requirements. Confidence in successful S-IVB restarts was also high. For the lunar missions, therefore, direct launch was considered as a fall-back position and the effort was concentrating on the parking orbit mode.
The Saturn 503 S-IVB stage exploded and was destroyed at the Douglas Sacramento, Calif., Test Facility at 4:25 p.m. PST during a countdown. The exercise had progressed to 10 seconds before simulated launch (about 8 minutes before S-IVB ignition) when the explosion occurred. Additional Details: Apollo S-IVB stage for Saturn launch vehicle 503 exploded.
Apollo Program Director Samuel C. Phillips sent a message to the manned space flight Centers indicating that he wanted to supplement the findings of the S-IVB Accident Investigation Board with a review by the Crew Safety Panel of the possible impact on manned Apollo flights. He requested Crew Safety Panel members and any other necessary crew safety representatives to go to Sacramento, Calif., immediately, review the 20 January accident, and answer a number of questions:
NASA Deputy Administrator Robert C. Seamans, Jr., reported to Administrator James E. Webb on progress of the Apollo 204 Review Board investigation of the January 27 spacecraft fire. Specific cause of the fire had not been determined from the preliminary review. Official death certificates for the three crew members listed cause of death as "asphyxiation due to smoke inhalation due to the fire." Webb released the report to Congress and the press.
Associate Administrator for Manned Space Flight George E. Mueller announced that the unmanned flights AS-206 (on uprated Saturn I) an AS-501 and AS-502 (first and second Saturn V launches) would proceed as scheduled in 1967. Manned flights were postponed indefinitely.
MSC Director Robert R. Gilruth asked LaRC Director Floyd Thompson to conduct a study at Langley to familiarize flight crews with CM active docking and to explore problems in CM recontact with the LM and also LM withdrawal. MSC would provide astronaut and pilot-engineer support for the study. Apollo Block II missions called for CM active docking with the LM and withdrawal of the LM from the S-IVB stage, requiring development of optimum techniques and procedures to ensure crew safety and to minimize propellant utilization. LM withdrawal was a critical area because of clearances, marginal flight crew visibility, and mission constraints. Previous simulations at LaRC indicated the possibility of using the Rendezvous Docking Simulator.
The Board of Inquiry into the January 20 S-IVB-503 explosion at the Douglas Sacramento Test Facility identified the probable cause as the failure of a pressure vessel made with titanium-alloy parent-metal fusion welded with commercially pure titanium. The combination, which was in violation of specifications, formed a titanium hydride intermetallic that induced embrittling in the weld nugget, thus significantly degrading the capabilities of a weldment to withstand sustained pressure loads. The Board recommended pressure limitations for titanium-alloy pressure vessels.
NASA Deputy Administrator Robert C. Seamans, Jr., informed Associate Administrator for Manned Space Flight George E. Mueller that, in view of the interim nature of schedule outlook for manned uprated Saturn I and Saturn V missions, he had decided to show these missions as "Under Study" in the Official NASA Flight Schedule for February 1967. As soon as firm approved dates for the missions were available the schedule would be updated. He said that all participants in the Apollo program should be advised that - except for unmanned missions 206, 501, and 502 - official agency schedule commitments had not been made and certainly could not be quoted until management assessments of the program had been completed and schedules approved by the Office of the Administrator.
During a House Committee on Science and Astronautics hearing on NASA's FY 1968 authorization, NASA Administrator James E. Webb replied to questions by Congressmen John W. Wydler, Edward J. Gurney, and Emilio Q. Daddario about the impact of the Apollo 204 accident on schedules for accomplishing the lunar landing. Additional Details: Impact of the Apollo 204 accident on schedules.
NASA Associate Administrator for Manned Space Flight George E. Mueller stated that the February completion of MSFC studies of the Saturn V launch vehicle's payload and structural capability would permit an official revision of the payload from 43,100 kilograms to 44,500 kilograms; the CM weight would be revised from 5,000 to 5,400 kilograms; and the LM from 13,600 to 14,500.
MSC Director of Flight Crew Operations Donald K. Slayton requested that a rendezvous of the CSM with its launch vehicle S-IVB stage be a primary objective of the Apollo 2 mission (i.e., Apollo 7; Slayton apparently wanted to acknowledge only scheduled manned flights in the sequentially numbered Apollo missions). He stated that the exercise could be conducted after the third darkness without interference with normal spacecraft checkout. "We believe a rendezvous with the booster on the first manned Apollo mission would be compatible with developing lunar mission capability at the earliest opportunity and request its incorporation into the primary mission objective." A memorandum from Flight Operations Director Christopher C. Kraft, Jr., on April 18 recognized "the need for CSM active rendezvous early in the Apollo flight program, but recommends that rendezvous not be considered during the first day of the Apollo 7 (the official flight designation for the first manned flight) mission. . . ." and presented four reasons:
NASA Hq. Office of Manned Space Flight informed KSC, MSFC, and MSC of approved designations for Apollo and Apollo Applications missions:
In reply to a request from NASA Hq., CSM Manager Kenneth S. Kleinknecht told Apollo Program Director Samuel C. Phillips that replacement of the service module 017 oxidizer tank was based on a double repair weld of the method 2 kind in that tank. This kind of repair, he said, resulted in a weld chemistry similar to the weld on the S-IVB helium bottle that had failed, as had only recently been determined by examination of the secondary-propulsion-system tank repair weld. There was insufficient proof that titanium hydride concentrations could not occur in the double method-2 repair weld, and replacement of the tank would preclude any question as to the integrity of the tank. The decision was delayed as long as possible in the hope of developing technical justification of weld integrity. When that was not achieved and there was little confidence that justification could be developed in the near future, the decision was made directing the tank change. The activity would not cause additional schedule time loss, as it was already necessary to repeat the spacecraft integrated test because of wiring rework.
![]() | Saturn V Title 9,216 bytes. 137 x 413 pixels. |
NASA Hq. informed the Directors of the manned space flight Centers that responsibility for approval of pressure vessel tests was being returned to normal Center management channels. Because of the failure of the 503 launch vehicle S-IVB stage and other pressure vessel problems, testing had been restricted by the office of the Apollo Program Director. The Program Director now returned to the Center Directors "responsibility for approving pressurization tests of pressure vessels in spacecraft modules, launch vehicle stages, and ground support equipment within their Apollo program responsibilities."
A meeting at MSC considered requirements of the Apollo flight program before the first lunar landing mission. Present were C. H. Perrine, MSC Mission Operations Division, and Christopher C. Kraft, Jr., Sigurd A. Sjoberg, John D. Hodge, Eugene F. Kranz, Morris V. Jenkins, and Robert E. Ernull, all of Flight Operations Directorate. Most significant opinions resulting from the meeting were:
NASA Apollo Program Director Samuel C. Phillips signed a directive defining the requirements, responsibilities, and inter-Center coordination necessary for development, control, and execution of test and checkout plans and procedures for preparing and launching Apollo-Saturn space vehicles at KSC.
After review of operational considerations for a minimum restart capability in the Saturn launch vehicle's S IVB stage, MSC's Director of Flight Operations reported to NASA Hq. that an 80-minute restart capability was believed the best compromise for the early lunar missions, "for the primary reason of providing sufficient time for ground support in verifying navigation, and flight crew checkout of CSM and S-IVB systems prior to TLI (translunar injection), while providing for two injection opportunities in both the Atlantic and Pacific Oceans (second and third revolutions). For later missions, consideration should be given to the hardware implications of providing a restart capability with minimum (zero) restrictions, so that advantage may be taken of confidence in onboard systems to gain additional payload."
A Block II spacecraft vibration program was begun to provide confidence in CSM integrity and qualify the hardware interconnecting the subsystems within the spacecraft. A test at MSC was to simulate the vibration environment of max-q flight conditions. The test article was to be a Block II CSM. A spacecraft-LM adapter, an instrumentation unit, and an S-IVB stage forward area simulation would also be used.
Because of the Apollo 204 accident in January and the resulting program delays, NASA realigned its Apollo and AAP launch schedules. The new AAP schedule called for 25 Saturn IB and 14 Saturn V launches. Major hardware for these launches would be two Workshops flown on Saturn IB vehicles, two Saturn V Workshops, and three ATMs. Under this new schedule, the first Workshop launch would come in January 1969.
Apollo Program Director Samuel C. Phillips, in a message to ASPO Manager George M. Low, spoke of a June 2 agreement to include a CSM active rendezvous with the Saturn S-IVB stage of the launch vehicle in the mission profile of the first manned Apollo mission. Phillips said that it should be recognized that such a rendezvous would not be a primary objective for the first manned mission and that the decision should be reviewed if any related problem that would complicate mission preparations were identified.
H. G. Paul, Chief of Marshal Space Flight Center's Propulsion Division, said it had come to the attention of his office that spacecraft/S-IVB rendezvous to within approximately 100 meters was being considered for the AS-205 mission. The division's position was that, unless the S-IVB stage were made passive, the division could not guarantee the stage would be in a safe condition. After the lifetime of a nonpassivated stage, it was possible that indiscriminant propellant-tank or bottle venting could cause the stage to tumble, thus permitting liquid to enter the propellant-tank vent lines. Another area of concern was the high-pressure bottles on the stage. Should a relief valve fail to function normally, a bottle rupture could result. The Propulsion Division therefore recommended that no rendezvous mission be planned with S-IVB stages of either Saturn IB or Saturn V launch vehicles after the guaranteed lifetime of the stage, unless that stage had been passivated.
Apollo spacecraft 017 was mechanically mated to its Saturn V launch vehicle at KSC in preparation for the Apollo 4 (AS-501) unmanned mission, scheduled for the third quarter of 1967.
This contract marked the first Saturn V procurement in support of Apollo Applications Program.
Rocketdyne Division of North American Aviation was selected for negotiation of a contract for the design, development, qualification, and delivery of four production models of an injector for the lunar module ascent engine. The project would serve as a backup to the injector program already being conducted by Bell Aerospace Corp. under subcontract to Grumman. The ascent engine was considered to be the most critical engine in the Apollo-Saturn vehicle. No backup mode of operation remained if the ascent engine failed.
Before the Apollo 1 fire, it was planned that McDivitt's crew would conduct the Apollo D mission - a first manned test in earth orbit of the Lunar Module. Separate Saturn IB launches would put Apollo Block II CSM 101 / AS-207 and Lunar Module LM-2 / AS-208 into earth orbit. The crew would then rendezvous and dock with the lunar module and put it through its paces. After the fire, it was decided to launch the mission on a single Saturn V as Apollo 9. CSM-101 instead would be used to accomplish the Apollo C mission that Grissom's crew was to have flown.
When Schirra's Apollo 2 / AS-205 mission was cancelled in November 1966, the booster went to McDivitt's mission, and it was called AS (or Apollo) 205/208, or AS-258 (before Schirra's cancellation, McDivitt's was AS-278, because it used Saturn IB boosters 207 and 208).
Apollo Program Director Samuel C. Phillips was appointed Chairman of a NASA task group, reporting to Administrator James E. Webb, Deputy Administrator Robert C. Seamans, Jr., and Associate Administrator for Manned Space Flight George E. Mueller. The group was chartered to review the content of the Apollo program in order to determine alternatives necessary for programming and budget planning decisions. It would inquire into and report on all aspects of the Apollo program necessary to provide a base of accurate data and information to support decisions on FY 1968 expenditure control and FY 1969 budget planning. Specifically, the group was requested to identify planned activities that could be eliminated if the Apollo program were to be terminated with the manned lunar landing. The group was also requested to determine the effect of placing a hold order on production of Saturn V vehicles 512 through 515 and to develop the cost estimates resulting from these actions as well as other tangible alternatives.
MSC proposed to the NASA Office of Manned Space Flight a sequence of missions leading to a lunar landing mission. The sequence included the following basic missions:
![]() | Saturn V LV Credit: © Mark Wade. 1,801 bytes. 84 x 462 pixels. |
NASA Hq issued a revised AAP schedule incorporating recent budgetary cutbacks. The schedule reflected the reduction of AAP lunar activity to four missions and of Saturn V Workshop activity to 17 Saturn IB and 7 Saturn V launches. There would be two Workshops launched on Saturn IBs, one Saturn V Workshop, and three ATMs. Launch of the first Workshop was scheduled for March 1970.
Because of wind conditions, an abort of the Apollo spacecraft from a Saturn V in the near-pad region would result in land impact. To ensure the maximum potential safe recovery of the crew during a near-pad abort, certain forms of preparation within the abort area were being considered. Tests were being prepared at MSC and KSC to determine the most favorable soil condition for spacecraft landing. The capability of the spacecraft to sustain a land impact was also being investigated by MSC.
NASA announced an Apollo mission schedule calling for six flights in 1968 and five in 1969. NASA Associate Administrator for Manned Space Flight George E. Mueller said the schedule and alternative plans provided a schedule under which a limited number of Apollo command and service modules and lunar landing modules, configured for lunar landing might be launched on test flights toward the moon by the end of the decade. Apollo/uprated Saturn I flights were identified with a 200 series number; Saturn V flights were identified with a 500 series number. Additional Details: Apollo mission schedule for six flights in 1968 and five in 1969.
Apollo 4 (AS-501) was launched in the first all-up test of the Saturn V launch vehicle and also in a test of the CM heatshield. The Saturn V, used for the first time, carried a lunar module test article (LTA-10R) and a Block I command and service module (CSM 017) into orbit from KSC Launch Complex 39, Pad A, lifting off at 7:00:01 a.m. EST - one second later than planned. The launch was also the first use of Complex 39. The spacecraft landed 8 hours 37 minutes later in the primary recovery area in the Pacific Ocean, near Hawaii, about 14 kilometers from the planned point (30.06 N 172.32 W). CM, apex heatshield, and one main parachute were recovered by the carrier U.S.S. Bennington
Main objectives of the mission were to demonstrate the structural and thermal integrity of the space vehicle and to verify adequacy of the Block II heatshield design for entry at lunar return conditions. These objectives were accomplished.
The S-IC stage cutoff occurred 2 minutes 30 seconds into the flight at an altitude of about 63 kilometers. The S-II stage ignition occurred at 2 minutes 32 seconds and the burn lasted 6 minutes 7 seconds, followed by the S-IVB stage ignition and burn of 2 minutes 25 seconds. This series of launch vehicle operations placed the S-IVB and spacecraft combination in an earth parking orbit with an apogee of about 187 kilometers and a perigee of 182 kilometers. After two orbits, which required about three hours, the S-IVB stage was reignited to place the spacecraft in a simulated lunar trajectory. This burn lasted five minutes. Some 10 minutes after completion of the S-IVB burn, the spacecraft and S-IVB stage were separated, and less than 2 minutes later the service propulsion subsystem was fired to raise the apogee. The spacecraft was placed in an attitude with the thickest side of the CM heatshield away from the solar vector. During this four-and-one-half-hour cold-soak period, the spacecraft coasted to its highest apogee - 18,256.3 kilometers. A 70 mm still camera photographed the earth's surface every 10.6 seconds, taking 715 good-quality, high-resolution pictures.
About 8 hours 11 minutes after liftoff the service propulsion system was again ignited to increase the spacecraft inertial velocity and to simulate entry from a translunar mission. This burn lasted four and one half minutes. The planned entry velocity was 10.61 kilometers per second, while the actual velocity achieved was 10.70.
Recovery time of 2 hours 28 minutes was longer than anticipated, with the cause listed as sea conditions - 2.4-meter swells.
MSC informed MSFC that it would provide the following payload flight hardware for the AS-503/BP-30 flight test: boilerplate 30 (BP-30, already at MSFC); spacecraft-LM adapter 101 and launch escape system (SLA-101/LES) jettisonable mass simulation; and lunar module test article B (LTA-B, already at MSFC). MSC had no mission requirements but recommended that any restart test requirements for the Saturn S-IVB stage be carried out on this mission to simplify requirements for the first manned Saturn V mission.
NASA Hq. announced that, as concurred in by the Center Apollo Program Managers, the following decisions, based on the results of the Apollo 4 mission, were firmly established:
Apollo Program Director Samuel C. Phillips wrote the manned space flight Centers of Apollo schedule decisions. In a September 20 meeting at MSC to review the Apollo test flight program, MSC had proposed a primary test flight plan including
NASA budgetary restraints required an additional cut in AAP launches. The reduced program called for three Saturn IB and three Saturn V launches, including one Workshop launched on a Saturn IB, one Saturn V Workshop, and one ATM. Two lunar missions were planned. Launch of the first Workshop would be in April 1970.
George E. Mueller, NASA OMSF, in a letter to MSC Director Robert R. Gilruth, summarized a number of key Apollo program decisions required in order to emphasize the urgency of priority action in preparations necessary to certify the Apollo system design for manned flight. Mueller listed five items:
Nomenclature for the OWS included in the AAP presented in the FY 1969 budget was confirmed by NASA. The ground-outfitted OWS to be launched with Saturn V would be designated the 'Saturn V Workshop.' (This had sometimes been called the 'dry Workshop.') The OWS that would be launched by a Saturn IB would be referred to as the 'Saturn I Workshop.' (Colloquially it had been referred to as the 'wet workshop.') Terminology 'Uprated Saturn I' would not be used officially. This launch vehicle would be referred to as the 'Saturn IB.'
Apollo 6 (AS-502) was launched from Complex 39A at Kennedy Space Center. The space vehicle consisted of a Saturn V launch vehicle with an unmanned, modified Block I command and service module (CSM 020) and a lunar module test article (LTA-2R).
Liftoff at 7:00 a.m. EST was normal but, during the first-stage (S-IC) boost phase, oscillations and abrupt measurement changes were observed. During the second-stage (S-II) boost phase, two of the J-2 engines shut down early and the remaining three were extended approximately one minute to compensate. The third stage (S-IVB) firing was also longer than planned and at termination of thrust the orbit was 177.7 x 362.9 kilometers rather than the 160.9-kilometer near-circular orbit planned. The attempt to reignite the S-IVB engine for the translunar injection was unsuccessful. Reentry speed was 10 kilometers per second rather than the planned 11.1, and the spacecraft landed 90.7 kilometers uprange of the targeted landing point.
The most significant spacecraft anomaly occurred at about 2 minutes 13 seconds after liftoff, when abrupt changes were indicated by strain, vibration, and acceleration measurements in the S-IVB, instrument unit, adapter, lunar module test article, and CSM. Apparently oscillations induced by the launch vehicle exceeded the spacecraft design criteria.
The second-stage (S-II) burn was normal until about 4 minutes 38 seconds after liftoff; then difficulties were recorded. Engine 2 cutoff was recorded about 6 minutes 53 seconds into the flight and engine 3 cutoff less than 3 seconds later. The remaining second-stage engines shut down at 9 minutes 36 seconds - 58 seconds later than planned.
The S-IVB engine during its first burn, which was normal, operated 29 seconds longer than programmed. After two revolutions in a parking orbit, during which the systems were checked, operational tests performed, and several attitude maneuvers made, preparations were completed for the S-IVB engine restart. The firing was scheduled to occur on the Cape Kennedy pass at the end of the second revolution, but could not be accomplished. A ground command was sent to the CSM to carry out a planned alternate mission, and the CSM separated from the S-IVB stage.
A service propulsion system (SPS) engine firing sequence resulted in a 442-second burn and an accompanying free-return orbit of 22,259.1 x 33.3 kilometers. Since the SPS was used to attain the desired high apogee, there was insufficient propellant left to gain the high-velocity increase desired for the entry. For this reason, a complete firing sequence was performed except that the thrust was inhibited.
Parachute deployment was normal and the spacecraft landed about 9 hours 50 minutes after liftoff, in the mid-Pacific, 90.7 kilometers uprange from the predicted landing area (27.40 N 157.59 W). A normal retrieval was made by the U.S.S. Okinawa, with waves of 2.1 to 2.4 meters.
The spacecraft was in good condition, including the unified crew hatch, flown for the first time. Charring of the thermal protection was about the same as that experienced on the Apollo 4 spacecraft (CM 017).
Of the five primary objectives, three - demonstrating separation of launch vehicle stages, performance of the emergency detection system (EDS) in a close-loop mode, and mission support facilities and operations - were achieved. Only partially achieved were the objectives of confirming structure and thermal integrity, compatibility of launch vehicle and spacecraft, and launch loads and dynamic characteristics; and of verifying operation of launch vehicle propulsion, guidance and control, and electrical systems. Apollo 6, therefore, was officially judged in December as "not a success in accordance with . . . NASA mission objectives."
![]() | Saturn V No. b Credit: NASA. 16,329 bytes. 303 x 449 pixels. |
ASPO Manager George M. Low requested Joseph N. Kotanchik to establish a task team to pull together all participants in the dynamic analysis of the Saturn V and boost environment. He suggested that Donald C. Wade should lead the effort and that he should work with George Jeffs of North American Rockwell, Tom Kelly of Grumman and Wayne Klopfenstein of Boeing, and that Lee James of MSFC could be contacted for any desired support or coordination. The team would define the allowable oscillations at the interface of the spacecraft-LM adapter with the instrument unit for the existing Block II configuration, possible changes in the hardware to detune the CSM and the LM, and the combined effects of pogo and the S-IC single-engine-out case. Low also said he was establishing a task team under Richard Colonna to define a test program related to the same problem area and felt that Wade and Colonna would want to work together.
NASA Administrator James E. Webb approved plans to proceed with preparation of the third Saturn V space vehicle for a manned mission in the fourth quarter of 1968. The planned mission was to follow the unmanned November 9, 1967, Apollo 4 and April 4, 1968, Apollo 6 flights, launched on the first two Saturn V vehicles. NASA kept the option of flying another unmanned mission if further analysis and testing indicated that was the best course. Engineers had been working around the clock to determine causes of and solutions to problems met on the Apollo 6 flight.
ASPO Manager George M. Low informed Apollo Program Director Samuel C. Phillips of recent MSC work on the effects of launch vehicle-induced oscillations - i.e., "pogo" vibrations - on the spacecraft and its subsystems. MSC had made two key personnel assignments in this area:
NASA released a new AAP launch readiness and delivery schedule. The schedule decreased the number of Saturn flights to 11 Saturn IB flights and one Saturn V flight. It called for three Workshops. One of the Workshops would be launched by a Saturn IB, and another would serve as a backup. The third Workshop would be launched by a Saturn V. The schedule also included one ATM. Launch of the first Workshop would be in November 1970. Lunar missions were no longer planned in the AAP.
ASPO Manager George M. Low asked Aaron Cohen, one of his chief technical assistants, to investigate the ability of the Apollo spacecraft to withstand bending loads imposed by a failure of one or more engines on the Saturn V launch vehicle (as well as actual loads that would be imposed on the spacecraft). During the previous week, Low and the Configuration Control Board had ruled out making any significant design changes to cope with a Saturn V engine failure. Specifically, Low asked how bending loads on the spacecraft were derived; what bending loads were imposed on the spacecraft during the Apollo 6 mission, where two J-2 engines were cut off during the flight; what was the probability - and criticality - of an S-IC engine's failing and thereby imposing high bending loads; and whether abort limits should be established for an engine failure.
Prompted by a request from MSC to increase the Saturn V's performance to 46,070 kilograms for lunar missions, Samuel C. Phillips sought to strike a balance between spacecraft and launch vehicle weight-performance demands. He established as a new payload interface definition at translunar injection a payload of 46,040 kilograms. Should the vehicle per se be incapable of achieving this figure, said Phillips, he would relax certain flight constraints to achieve the best possible balance between the space vehicle and the specific mission to be flown. But he implored both ASPO Manager George M. Low and Lee B. James, Saturn V Program Manager at MSFC, to work toward this balance between spacecraft and launch vehicle and to avoid any hardware changes in the Saturn V solely to meet the new payload interface weight.
F. A. Speer, Mission Operations Manager at MSFC, advised NASA Hq. of plans for S-IVB and spacecraft separation and employment of a "slingshot" trajectory following insertion into the trajectory toward the moon. Residuals in the S-IVB, said Speer, could be used to place the stage in a trajectory that would avoid recontact with the spacecraft and impact on either the earth or the moon - with preclusion of spacecraft-launch vehicle collision as the most important priority.
The action involved 27 H-1, eight F-1, and three J-2 rocket engines.
ASPO Manager George M. Low initiated a series of actions that led to the eventual decision that AS-503 (Apollo 8) should be a lunar orbital mission. Additional Details: Decision that Apollo 8 should be a lunar orbital mission.
Dieter Grau, Director of Quality and Reliability Assurance at MSFC, sent his Houston counterpart Martin Raines a memorandum of understanding covering exchanges of quality surveillance responsibility in support of pogo structural testing under way both in Huntsville, Ala., and at MSC. Testing was being conducted simultaneously at the Wyle Laboratories in Huntsville (under contract to North American Rockwell, primarily static loading and referred to as shell stability tests); and dynamic load testing at MSC (called the "short stack" dynamic tests). In effect, each Center assumed the task of overseeing the complete test article (spacecraft, instrument unit, and S-IVB forward skirt) being tested at its own location.
ASPO Manager George M. Low wrote Program Director Samuel C. Phillips seeking to halt further development of a pogo sensor for the CSM. (MSC had undertaken development of the device shortly after the Apollo 6 flight as "insurance" should the sensor prove necessary.) No requirement for a pogo sensor had been identified, said Low. In fact, it was by no means certain how the sensor could be used in flight. Because MSFC was highly confident that the pogo problem encountered on Apollo 6 had been solved, and because no abort criteria could be based on pogo alone, Low argued against the sensor. Even in the unlikely event that pogo occurred on the next Saturn V flight, he argued against an abort unless there was a catastrophic effect on the launch vehicle, in which case abort would be effected using normal abort criteria. For these reasons, no pogo sensor was to be installed on the CSM. A week later, Phillips approved Low's recommendation to halt the pogo sensor development.
In a Mission Preparation Directive sent to the three manned space flight Centers, NASA Apollo Program Director Samuel C. Phillips stated that the following changes would be effected in planning and preparation for Apollo flights:
ASPO Manager George M. Low asked Joseph N. Kotanchik, head of the Structures and Mechanics Division, to verify that all spacecraft load analyses and safety factors were compatible with the recently agreed-on payload weight of 39,780 kilograms for the AS-503 mission. Low passed along the concern voiced by Lee B. James, Saturn V Program Manager at MSFC, that the problem of an S-IC engine failure in the Saturn launch vehicle might be more severe for the 503 mission than for a heavier payload. Had adequate stress analysis been done on the high-gain antenna attachments and its support inside the adapter? When would pogo dynamic analysis of the actual 503 payload be completed? And finally, what was the situation regarding loads on LTA-B, the LM test article to be substituted in place of an actual lunar lander aboard the flight?
George M. Low, ASPO Manager, set forth the rationale for using LTA-B (as opposed to some other LM test article or even a full-blown LM) as payload ballast on the AS-503 mission. That decision had been a joint one by Headquarters, MSFC, and MSC. Perhaps the chief reason for the decision was Marshall's position that the Saturn V's control system was extremely sensitive to payload weight. Numerous tests had been made for payloads of around 38,555 kilograms but none for those in the 29,435- to 31,750-kilogram range. MSFC had therefore asked that the minimum payload for AS-503 be set at 38,555 kilograms. Additional Details: Decision to use Apollo LTA-B as payload ballast on the AS-503 flight.
The Apollo Crew Safety Review Board, headed by William C. Schneider, met for the third time at MSFC, a meeting devoted primarily to safety factors for the Saturn V launch vehicle. Of particular concern was the capability to shut down the vehicle during the period between ignition and liftoff should some problem arise (it could be shut down by several methods, including both manual and automatic engine shutdown). The Board also reviewed in detail Saturn V modifications that had eliminated more than 50 engine and electrical circuitry potential single-point failures (primarily through increased redundancy and circuitry checkout). Similarly the Board examined the reliability of guidance failure indicators and checkout of the emergency detection system during the final portion of the countdown. No additional action was needed, members concluded, because all functions in the launch vehicle were checked during the terminal count and tank pressure gauges were checked out by disconnecting the transducers and testing them individually several days before launch.
At the end of the meeting, Board members attended the POGO Management Review, where they were favorably impressed by the optimism among Saturn V program officials that the pogo problem had been solved (although contingency planning for a pogo occurrence should continue through AS-503).
Apollo Program Director Samuel C. Phillips formally notified ASPO Manager George M. Low at MSC and Saturn V Program Manager Lee B. James at MSFC of changes in the Apollo Program Specification. As agreed on during the MSF Management Council meeting on August 6, the Apollo payload interface was set at 46,040 kilograms (with a flight geometry reserve of 137 kilometers per hour). Also, the present spacecraft loading philosophy allowed a total spacecraft weight of 46,266 kilograms for lunar missions having less than maximum flight geometry requirements. Additional Details: Changes in the Apollo Program Specification.
Apollo Program Director Samuel C. Phillips wrote to his two principal counterparts at MSFC and MSC, Lee B. James and George M. Low, to express his concern that the launch-release wind constraint for the Saturn IB, currently 45 kilometers, was perhaps the most restrictive of all such constraints. Phillips emphasized his need for a complete understanding of all tradeoffs associated with this figure, to allow a real-time estimate of the requirement to hold. He asked James and Low to summarize for him several such tradeoffs before the Apollo 7 flight readiness review: wind versus safety, velocity versus direction, and conservative assumption versus technical accuracy. Also, he asked for criticality and failure mode for each of the above tradeoffs to allow a technical evaluation of increasing the 45-kilometer constraint. At the same time, he asked that a similar effort be initiated for the Saturn V.
The Apollo Crew Safety Review Board held its fourth meeting at MSC. Discussions centered chiefly on Saturn V engine-out abort situations and the ability of the CSM to withstand structural loads imposed by such vehicle failures. In fact, however, it was unlikely that any problem would be experienced, because of a controlled S-IC engine shutdown. Loads because of catastrophic engine failure greatly exceeded spacecraft capability, but the Board ruled such an occurrence as remote and accepted it as a flight risk. Also, evaluation of testing results demonstrated that overall loads because of pogo vibration were not a problem. Board Chairman William C. Schneider reported that, in general, action items assigned to MSC as a result of the Apollo 7 review had been satisfactorily closed.
In preparation for the flight of Apollo 8, NASA and industry technicians at KSC placed CSM 103 atop the Saturn V launch vehicle. The launch escape system was installed the following day; and on October 9 the complete AS-503 space vehicle was rolled out of the Vehicle Assembly Building and moved to the launch pad, where launch preparations were resumed.
Apollo Program Director Samuel C. Phillips ordered that the Saturn IB program be placed in a standby status pending any future requirements for Apollo or the Apollo Applications program. Phillips' action signaled the shift in Apollo to the Saturn V vehicle, effective with AS-503.
Howard D. Burns, Chief of the Saturn V Test Management Office at MSFC, sent to Apollo launch operations officials at KSC a list of requirements for retesting the Saturn V following a lightning strike on the vehicle while on the pad. Additional Details: Retesting Saturn V following a lightning strike.
ASPO Manager George M. Low asked Rocco A. Petrone, Launch Operations Director at KSC, to set up a special task team to review all paperwork and to inspect visually all hardware, to ensure proper spacecraft deployment during the Apollo 8 flight. Apollo 8 contained a novel set of mechanical and electrical interfaces (CSM, LTA-B lunar module dummy, launch adapter, and Saturn V vehicle), Low observed. Furthermore, concern about these complex interfaces had increased because one of the adapter panels on Apollo 7 had not opened properly. What Low - as well as MSC Director Robert R. Gilruth - desired foremost was to preclude repetition of another situation such as had occurred during the Gemini IX mission, when the shroud panels covering the Agena target vehicle had only partially deployed and had produced the "angry alligator" that forced cancellation of docking plans on that earlier flight.
Launch preparations for Apollo 8, scheduled for flight December 21, were on schedule, the NASA Associate Administrator for Manned Space Flight reported. Recent significant steps included a leak and functional test of the service propulsion system on November 26, fuel servicing of the CM reaction control system and the SPS on the following day, hypergolic loading on November 30, and loading of the S-IC stage with RP-1 fuel on December 2. All testing of the Mission Control Center in Houston and the Manned Space Flight Network had also been completed; both support systems were ready for full operational support. Recovery briefings had been given to the flight crew and the final flight plan for Apollo 8 had been issued. If all preparations continued to go smoothly, the final countdown for launch would begin on December 16.
Apollo 8 (AS-503) was launched from KSC Launch Complex 39, Pad A, at 7:51 a.m. EST Dec. 21 on a Saturn V booster. The spacecraft crew was made up of Frank Borman, James A. Lovell, Jr., and William A. Anders. Apollo 8 was the first spacecraft to be launched by a Saturn V with a crew on board, and that crew became the first men to fly around the moon.
All launch and boost phases were normal and the spacecraft with the S-IVB stage was inserted into an earth-parking orbit of 190.6 by 183.2 kilometers above the earth. After post-insertion checkout of spacecraft systems, the S-IVB stage was reignited and burned 5 minutes 9 seconds to place the spacecraft and stage in a trajectory toward the moon - and the Apollo 8 crew became the first men to leave the earth's gravitational field.
The spacecraft separated from the S-IVB 3 hours 20 minutes after launch and made two separation maneuvers using the SM's reaction control system. Eleven hours after liftoff, the first midcourse correction increased velocity by 26.4 kilometers per hour. The coast phase was devoted to navigation sightings, two television transmissions, and system checks. The second midcourse correction, about 61 hours into the flight, changed velocity by 1.5 kilometers per hour.
The 4-minute 15-second lunar-orbit-insertion maneuver was made 69 hours after launch, placing the spacecraft in an initial lunar orbit of 310.6 by 111.2 kilometers from the moon's surface - later circularized to 112.4 by 110.6 kilometers. During the lunar coast phase the crew made numerous landing-site and landmark sightings, took lunar photos, and prepared for the later maneuver to enter the trajectory back to the earth.
On the fourth day, Christmas Eve, communications were interrupted as Apollo 8 passed behind the moon, and the astronauts became the first men to see the moon's far side. Later that day , during the evening hours in the United States, the crew read the first 10 verses of Genesis on television to earth and wished viewers "goodnight, good luck, a Merry Christmas and God bless all of you - all of you on the good earth."
Subsequently, TV Guide for May 10-16, 1969, claimed that one out of every four persons on earth - nearly 1 billion people in 64 countries - heard the astronauts' reading and greeting, either on radio or on TV; and delayed broadcasts that same day reached 30 additional countries.
On Christmas Day, while the spacecraft was completing its 10th revolution of the moon, the service propulsion system engine was fired for three minutes 24 seconds, increasing the velocity by 3,875 km per hr and propelling Apollo 8 back toward the earth, after 20 hours 11 minutes in lunar orbit. More television was sent to earth on the way back and, on the sixth day, the crew prepared for reentry and the SM separated from the CM on schedule.
Parachute deployment and other reentry events were normal. The Apollo 8 CM splashed down in the Pacific, apex down, at 10:51 a.m. EST, December 27 - 147 hours and 42 seconds after liftoff. As planned, helicopters and aircraft hovered over the spacecraft and pararescue personnel were not deployed until local sunrise, 50 minutes after splashdown. The crew was picked up and reached the recovery ship U.S.S. Yorktown at 12:20 p.m. EST. All mission objectives and detailed test objectives were achieved, as well as five that were not originally planned.
The crew was in excellent condition, and another major step toward the first lunar landing had been accomplished. Additional Details: Apollo 8.
Mass model of lunar module with docking target remained attached to S-IVB translunar injection stage.
MSFC announced that Arthur Rudolph, special assistant to the MSFC Director, would retire January 31. Rudolph had served as the manager of the Saturn V rocket program from August 1963 to May 1968. He was one of the more than 100 rocket experts who came to the United States from Germany in 1945. The MSC ASPO Manager, in a congratulatory letter said, "I will always consider Saturn V to be one of the outstanding achievements that occurred during my lifetime. Its sheer size is simply fantastic. But even more astounding was its performance in its first flights." Rudolph's work in bringing the nation's most powerful launch vehicle to flight status was rewarded when the first Saturn V lifted off from KSC and performed flawlessly on November 9, 1967, Rudolph's birthday.
The final flight program for Apollo 9 was verified; the emergency egress test with the prime and backup crew was conducted; and the software integration test between the lunar module and Mission Control Center, MSC, was completed on January 15. On January 16 the Saturn V/Mission Control Center-Houston integration testing was conducted. Additionally, a critical design review of the Launch Complex 39 slide wire system was conducted on January 17. Launch preparations for Apollo 9 continued to proceed on schedule.
Apollo 9 (AS-504), the first manned flight with the lunar module (LM-3), was launched from Pad A, Launch Complex 39, KSC, on a Saturn V launch vehicle at 11:00 a.m. EST March 3. Originally scheduled for a February 28 liftoff, the launch had been delayed to allow crew members James A. McDivitt, David R. Scott, and Russell L. Schweickart to recover from a mild virus respiratory illness. Following a normal launch phase, the S-IVB stage inserted the spacecraft into an orbit of 192.3 by 189.3 kilometers. After post-insertion checkout, CSM 104 separated from the S-IVB, was transposed, and docked with the LM. At 3:08 p.m. EST, the docked spacecraft were separated from the S-IVB, which was then placed on an earth-escape trajectory.
On March 4 the crew tracked landmarks, conducted pitch and roll yaw maneuvers, and increased the apogee by service propulsion system burns.
On March 5 McDivitt and Schweickart entered the LM through the docking tunnel, evaluated the LM systems, transmitted the first of two series of telecasts, and fired the LM descent propulsion system. They then returned to the CM.
McDivitt and Schweickart reentered the LM on March 6. After transmitting a second telecast, Schweickart performed a 37-minute extravehicular activity (EVA), walking between the LM and CSM hatches, maneuvering on handrails, taking photographs, and describing rain squalls over KSC.
On March 7, with McDivitt and Schweickart once more in the LM, Scott separated the CSM from the LM and fired the reaction control system thrusters to obtain a distance of 5.5 kilometers between the two spacecraft. McDivitt and Schweickart then performed a lunar-module active rendezvous. The LM successfully docked with the CSM after being up to 183.5 kilometers away from it during the six-and-one-half-hour separation. After McDivitt and Schweickart returned to the CSM, the LM ascent stage was jettisoned.
During the remainder of the mission, the crew tracked Pegasus III, NASA's meteoroid detection satellite that had been launched July 30, 1965; took multispectral photos of the earth; exercised the spacecraft systems; and prepared for reentry.
The Apollo 9 CM splashed down in the Atlantic 290 kilometers east of the Bahamas at 12:01 p.m. EST. The crew was picked up by helicopter and flown to the recovery ship U.S.S. Guadalcanal within one hour after splashdown. Primary objectives of the flight were successfully accomplished. Additional Details: Apollo 9.
The additional direct cost to the Apollo research and development program from the January 27, 1967, Apollo 204 fire was estimated at $410 million, principally for spacecraft modifications, NASA Associate Administrator for Manned Space Flight George E. Mueller testified in congressional hearings. The accident delayed the first manned flight of the spacecraft by about 18 months. "During this period, however, there occurred a successful unmanned test of the Lunar Module and two unmanned tests of the Saturn V vehicle."
Following a report by the Apollo 9 astronauts that they were thrown forward in their seats and had to grab their arm rests for support during the S-IC/S-II stage separation, an evaluation working group were studying the problem. Preliminary results indicated that the separation transients were a dynamic characteristic of the Saturn V vehicle; that the measured accelerations were within predicted range and below design limits; and that the separation sequences were normal. Conclusions were that similar separation dynamics could be anticipated on future Saturn V flights.
A power outage, required to permit maintenance work at the KSC Launch Control Center, was relayed to the pneumatic controls of the S-IC stage of the Apollo 10 launch vehicle, causing the prevalves to open and allowing 5,280 liters of RP-1 fuel to drain from the vehicle. This, in turn, produced negative pressure in the RP-1 tank, which displaced the upper bulkhead.
After repressurization, the bulkhead apparently returned to its normal shape. An effort was under way to determine the nature of the damage to the bulkhead and the effect on the May 18 Apollo 10 launch readiness date.
A temporary fix to provide for an S-II-stage early center engine cutoff was made for Apollo 10 and 11. Purpose was to eliminate oscillations of the center engine and sympathetic structures. Meanwhile, plans were being made to incorporate a permanent fix into Apollo 12 and subsequent vehicles to eliminate the oscillations.
Final dress rehearsal in lunar orbit for landing on moon. LM separated and descended to 10 km from surface of moon but did not land. Apollo 10 (AS-505) - with crew members Thomas P. Stafford, Eugene A. Cernan, and John W. Young aboard - lifted off from Pad B, Launch Complex 39, KSC, at 12:49 p.m. EDT on the first lunar orbital mission with complete spacecraft. The Saturn V's S-IVB stage and the spacecraft were inserted into an earth parking orbit of 189.9 by 184.4 kilometers while the onboard systems were checked. The S-IVB engine was then ignited at 3:19 p.m. EDT to place the spacecraft in a trajectory toward the moon. One-half hour later the CSM separated from the S-IVB, transposed, and docked with the lunar module. At 4:29 p.m. the docked spacecraft were ejected, a separation maneuver was performed, and the S-IVB was placed in a solar orbit by venting residual propellants. TV coverage of docking procedures was transmitted to the Goldstone, Calif., tracking station for worldwide, commercial viewing.
On May 19 the crew elected not to make the first of a series of midcourse maneuvers. A second preplanned midcourse correction that adjusted the trajectory to coincide with a July lunar landing trajectory was executed at 3:19 p.m. The maneuver was so accurate that preplanned third and fourth midcourse corrections were canceled. During the translunar coast, five color TV transmissions totaling 72 minutes were made of the spacecraft and the earth.
At 4:49 p.m. EDT on May 21 the spacecraft was inserted into a lunar orbit of 110.4 by 315.5 kilometers. After two revolutions of tracking and ground updates, a maneuver circularized the orbit at 109.1 by 113.9 kilometers. Astronaut Cernan then entered the LM, checked all systems, and returned to the CM for the scheduled sleep period.
On May 22 activation of the lunar module systems began at 11:49 a.m. EDT. At 2:04 p.m. the spacecraft were undocked and at 4:34 p.m. the LM was inserted into a descent orbit. One hour later the LM made a low-level pass at an altitude of 15.4 kilometers over the planned site for the first lunar landing. The test included a test of the landing radar, visual observation of lunar lighting, stereo photography of the moon, and execution of a phasing maneuver using the descent engine. The lunar module returned to dock successfully with the CSM following the eight-hour separation, and the LM crew returned to the CSM.
The LM ascent stage was jettisoned, its batteries were burned to depletion, and it was placed in a solar orbit on May 23. The crew then prepared for the return trip to earth and after 61.5 hours in lunar orbit a service propulsion system TEI burn injected the CSM into a trajectory toward the earth. During the return trip the astronauts made star-lunar landmark sightings, star-earth horizon navigation sightings, and live television transmissions.
Apollo 10 splashed down in the Pacific at 12:52 p.m. EDT on May 26, 5.4 kilometers from the recovery ship. The crew was picked up and reached the recovery ship U.S.S. Princeton at 1:31 p.m. All primary mission objectives of evaluating performance and support and the detailed test objectives were achieved. Additional Details: Apollo 10.
Gilruth and Von Braun support decision to fly a complete integrated solution on a single Saturn V launch. Additional Details: Saturn V "dry" Workshop decision..
The early engineering evaluation of the Apollo 10 launch vehicle, Saturn V AS-505, indicated that the major flight objectives were accomplished. Indications were that all detailed test objectives were also accomplished.
The basic performance of the Saturn V was satisfactory, but the following problem areas were identified for more extensive investigation:
Studies were being conducted to determine the feasibility of intentionally impacting an S-IVB stage and an empty LM stage on the lunar surface after jettison, to gather geological data and enhance the scientific return of the seismology experiment. Data would be obtained with the ALSEP seismographic equipment placed on the lunar surface during the Apollo 11 or Apollo 12 flight. MSFC and Bellcomm were examining the possibility of the S-IVB jettison; MSC, the LM ascent stage jettison. Intentional impacting of the ascent stage for Apollo 11 was later determined not to be desirable.
First landing on moon. Apollo 11 (AS-506) - with astronauts Neil A. Armstrong, Michael Collins, and Edwin E. Aldrin, Jr., aboard - was launched from Pad A, Launch Complex 39, KSC, at 9:32 a.m. EDT July 16. The activities during earth-orbit checkout, translunar injection, CSM transposition and docking, spacecraft ejection, and translunar coast were similar to those of Apollo 10.
At 4:40 p.m. EDT July 18, the crew began a 96-minute color television transmission of the CSM and LM interiors, CSM exterior, the earth, probe and drogue removal, spacecraft tunnel hatch opening, food preparation, and LM housekeeping. One scheduled and two unscheduled television broadcasts had been made previously by the Apollo 11 crew.
The spacecraft entered lunar orbit at 1:28 p.m. EDT on July 19. During the second lunar orbit a live color telecast of the lunar surface was made. A second service-propulsion-system burn placed the spacecraft in a circularized orbit, after which astronaut Aldrin entered the LM for two hours of housekeeping including a voice and telemetry test and an oxygen-purge-system check.
At 8:50 a.m. July 20, Armstrong and Aldrin reentered the LM and checked out all systems. They performed a maneuver at 1:11 p.m. to separate the LM from the CSM and began the descent to the moon. The LM touched down on the moon at 4:18 p.m. EDT July 20. Armstrong reported to mission control at MSC, "Houston, Tranquillity Base here - the Eagle has landed." (Eagle was the name given to the Apollo 11 LM; the CSM was named Columbia.) Man's first step on the moon was taken by Armstrong at 10:56 p.m. EDT. As he stepped onto the surface of the moon, Armstrong described the feat as "one small step for a man - one giant leap for mankind."
Aldrin joined Armstrong on the surface of the moon at 11:15 p.m. July 20. The astronauts unveiled a plaque mounted on a strut of the LM and read to a worldwide TV audience, "Here men from the planet earth first set foot on the moon July 1969, A.D. We came in peace for all mankind." After raising the American flag and talking to President Nixon by radiotelephone, the two astronauts deployed the lunar surface experiments assigned to the mission and gathered 22 kilograms of samples of lunar soil and rocks. They then reentered the LM and closed the hatch at 1:11 a.m. July 21. All lunar extravehicular activities were televised in black-and-white. Meanwhile, Collins continued orbiting moon alone in CSM Columbia.
The Eagle lifted off from the moon at 1:54 p.m. EDT July 21, having spent 21 hours 36 minutes on the lunar surface. It docked with the CSM at 5:35 p.m. and the crew, with the lunar samples and film, transferred to the CSM. The LM ascent stage was jettisoned into lunar orbit. The crew then rested and prepared for the return trip to the earth.
The CSM was injected into a trajectory toward the earth at 12:55 a.m. EDT July 22. Following a midcourse correction at 4:01 p.m., an 18-minute color television transmission was made, in which the astronauts demonstrated the weightlessness of food and water and showed shots of the earth and the moon.
At 12:15 p.m. EDT July 24 the Apollo 11's command module Columbia splashed down in the mid-Pacific, about 24 kilometers from the recovery ship U.S.S. Hornet. Following decontamination procedures at the point of splashdown, the astronauts were carried by helicopter to the Hornet where they entered a mobile quarantine facility to begin a period of observation under strict quarantine conditions. The CM was recovered and removed to the quarantine facility. Sample containers and film were flown to Houston.
All primary mission objectives and all detailed test objectives of Apollo 11 were met, and all crew members remained in good health. Additional Details: Apollo 11.
NASA Administrator Thomas O. Paine approved the shift from a 'wet' to a 'dry' Orbital Workshop concept for AAP following a review presentation by program officials on the potential benefits of such a change. On 22 July, AAP Director William C. Schneider ordered program managers at the three Centers to implement the change, abandoning the idea of using a spent Saturn IB second stage for a Workshop and adopting the concept of a fully equipped 'dry' configuration-with the ATM integrated into the total payload-launched aboard a Saturn V. Additional Details: NASA Administrator Paine approved the shift from a "wet" to a "dry" Orbital Workshop for AAP..
During the Apollo 11 management debriefing, the ASPO Manager noted a number of items requiring investigation. During separation from the S-IVB stage, the CSM autopilot apparently had difficulty determining direction of rotation. After the CSM hatch removal, there was a strong odor of burnt material in the tunnel. The leveling device on one of the experiment packages did not work. The closeup stereo camera was hard to operate and tended to fall over. The temperature in the lunar module was too cold during sleep periods. The biological isolation garment was uncomfortably hot and its visor fogged. The crew observed flashes at the rate of about one per minute in the command module at night.
The new schedule called for seven Saturn IB and two Saturn V launches, with flight of the first Workshop slated for July 1972.
Program responsibility for the Saturn launch vehicles was divided, at the Headquarters level, between the Apollo Program Office and the Apollo Applications Program. Overall responsibility for the Saturn V remained with the Apollo Program Office, while overall responsibility for the Saturn IB vehicle was assigned to Apollo Applications.
Apollo 12 (AS-507)-with astronauts Charles Conrad, Jr., Richard F. Gordon, Jr., and Alan L. Bean as the crewmen-was launched from Pad A, Launch Complex 39, KSC, at 11:22 a.m. EST November 14. Lightning struck the space vehicle twice, at 36.5 seconds and 52 seconds into the mission. The first strike was visible to spectators at the launch site. No damage was done. Except for special attention given to verifying all spacecraft systems because of the lightning strikes, the activities during earth-orbit checkout, translunar injection, and translunar coast were similar to those of Apollo 10 and Apollo 11.
During the translunar coast astronauts Conrad and Bean transferred to the LM one-half hour earlier than planned in order to obtain full TV coverage through the Goldstone tracking station. The 56-minute TV transmission showed excellent color pictures of the CSM, the intravehicular transfer, the LM interior, the earth, and the moon.
At 10:47 p.m. EST, November 17, the spacecraft entered a lunar orbit of 312.6 x 115.9 kilometers. A second service propulsion system burn circularized the orbit with a 122.5-kilometer apolune and a 100.6-kilometer perilune. Conrad and Bean again transferred to the LM, where they perfomed housekeeping chores, a voice and telemetry test, and an oxygen purge system check. They then returned to the CM.
Conrad and Bean reentered the LM, checked out all systems, and at 10:17 p.m. EST on November 18 fired the reaction control system thrusters to separate the CSM 108 (the Yankee Clipper) from the LM-6 (the Intrepid). At 1:55 a.m. EST November 19, the Intrepid landed on the moon's Ocean of Storms, about 163 meters from the Surveyor III spacecraft that had landed April 19, 1967. Conrad, shorter than Neil Armstrong (first man on the moon, July 20), had a little difficulty negotiating the last step from the LM ladder to the lunar surface. When he touched the surface at 6:44 a.m. EST November 19, he exclaimed, "Whoopee! Man, that may have been a small step for Neil, but that's a long one for me."
Bean joined Conrad on the surface at 7:14 a.m. They collected a 1.9-kilogram contingency sample of lunar material and later a 14.8-kilogram selected sample. They also deployed an S-band antenna, solar wind composition experiment, and the American flag. An Apollo Lunar Surface Experiments Package with a SNAP-27 atomic generator was deployed about 182 meters from the LM. After 3 hours 56 minutes on the lunar surface, the two astronauts entered the Intrepid to rest and check plans for the next EVA.
The astronauts again left the LM at 10:55 p.m. EST November 19. During the second EVA, Conrad and Bean retrieved the lunar module TV camera for return to earth for a failure analysis, obtained photographic panoramas, core and trench samples, a lunar environment sample, and assorted rock, dirt, bedrock, and molten samples. The crew then examined and retrieved parts of Surveyor III, including the TV camera and soil scoop. After 3 hours 49 minutes on the lunar surface during the second EVA, the two crewmen entered the LM at 2:44 a.m. EST November 20. Meanwhile astronaut Gordon, orbiting the moon in the Yankee Clipper, had completed a lunar multispectral photography experiment and photographed proposed future landing sites.
At 9:26 a.m. EST November 20, after 31 hours 31 minutes on the moon, Intrepid successfully lifted off with 34.4 kilograms of lunar samples. Rendezvous maneuvers went as planned. The LM docked with the CSM at 12:58 p.m. November 20. The last 24 minutes of the rendezvous sequence was televised. After the crew transferred with the samples, equipment, and film to the Yankee Clipper, the Intrepid was jettisoned and intentionally crashed onto the lunar surface at 5:17 p.m. November 20, 72.2 kilometers southeast of Surveyor III. The crash produced reverberations that lasted about 30 minutes and were detected by the seismometer left on the moon.
At 3:49 p.m. EST November 21, the crew fired the service propulsion system engine, injecting the CSM into a transearth trajectory after 89 hours 2 minutes in lunar orbit. During the transearth coast, views of the receding moon and the interior of the spacecraft were televised, and a question and answer session with scientists and the press was conducted.
Parachute deployment and other reentry events occurred as planned. The CM splashed down in mid-Pacific at 3:58 p.m. EST November 24, 7.25 kilometers from the recovery ship, U.S.S. Hornet. The astronauts, wearing flight suits and biological face masks, were airlifted by helicopter from the CM to the recovery ship, where they entered the mobile quarantine facility. They would remain in this facility until arrival at the Lunar Receiving Laboratory, MSC. The Apollo 12 mission objectives were achieved and the experiments successfully accomplished. Additional Details: Apollo 12.
NASA had canceled the Apollo 20 mission and stretched out the remaining seven missions to six-month intervals, Deputy Administrator George M. Low told the press in an interview after dedication of the Lunar Science Institute (next to MSC in Houston). Budget restrictions had brought the decision to suspend Saturn V launch vehicle production after vehicle 515 and to use the Apollo 20 Saturn V to launch the first U.S. space station in 1972.
Apollo 13 (AS-508) was launched from Pad A, Launch Complex 39, KSC, at 2:13 p.m. EST April 11, with astronauts James A. Lovell, Jr., John L. Swigert, Jr., and Fred W. Haise, Jr., aboard. The spacecraft and S-IVB stage entered a parking orbit with a 185.5-kilometer apogee and a 181.5-kilometer perigee. At 3:48 p.m., onboard TV was begun for five and one-half minutes. At 4:54 p.m., an S-IVB burn placed the spacecraft on a translunar trajectory, after which the CSM separated from the S-IVB and LM Aquarius. (The crew had named lunar module 7 Aquarius and CSM 109 Odyssey.) The CSM then hard-docked with the LM. The S-IVB auxiliary propulsion system made an evasive maneuver after CSM/LM ejection from the S-IVB at 6:14 p.m. The docking and ejection maneuvers were televised during a 72-minute period in which interior and exterior views of the spacecraft were also shown.
At 8:13 p.m. EST a 217-second S-IVB auxiliary propulsion system burn aimed the S-IVB for a lunar target point so accurately that another burn was not required. The S-IVB/IU impacted the lunar surface at 8:10 p.m. EST on April 14 at a speed of 259 meters per second. Impact was 137.1 kilometers from the Apollo 12 seismometer. The seismic signal generated by the impact lasted 3 hours 20 minutes and was so strong that a ground command was necessary to reduce seismometer gain and keep the recording on the scale. The suprathermal ion detector experiment, also deployed by the Apollo 12 crew, recorded a jump in the number of ions from zero at the time of impact up to 2,500 shortly thereafter and then back to a zero count. Scientists theorized that ionization had been produced by 6,300 K to 10,300 K (6,000 degrees C to 10,000 degrees C) temperature generated by the impact or that particles had reached an altitude of 60 kilometers from the lunar surface and had been ionized by sunlight.
Meanwhile back in the CSM/LM, the crew had been performing the routine housekeeping duties associated with the period of the translunar coast. At 30:40 ground elapsed time a midcourse correction maneuver took the spacecraft off a free-return trajectory in order to control the arrival time at the moon. Ensuring proper lighting conditions at the landing site. The maneuver placed the spacecraft on the desired trajectory, on which the closest approach to the moon would be 114.9 kilometers.
At 10:08 p.m. EST April 13, the crew reported an undervoltage alarm on the CSM main bus B, rapid loss of pressure in SM oxygen tank No. 2, and dropping current in fuel cells 1 and 3 to a zero reading. The loss of oxygen and primary power in the service module required an immediate abort of the mission. The astronauts powered up the LM, powered down the CSM, and used the LM systems for power and life support. The first maneuver following the abort decision was made with the descent propulsion system to place the spacecraft back in a free-return trajectory around the moon. After the spacecraft swung around the moon, another maneuver reduced the coast time back to earth and moved the landing point from the Indian Ocean to the South Pacific.
About four hours before reentry on April 17, the service module was jettisoned and the crew took photographs and made visual observations of the damaged area. About one hour before splashdown the command module was powered up and the lunar module was jettisoned. Parachutes were deployed as planned, and the Odyssey landed in the mid-Pacific 6.4 kilometers from the recovery ship U.S.S. Iwo Jima at 1:07 p.m. EST April 17. The astronauts were picked up by helicopter and transported to the recovery ship less than an hour after splashdown. Additional Details: Apollo 13.
KSC awarded a contract to Reynolds, Smith, and Hills of Jacksonville, Florida, for architectural and engineering services in modification plans for adapting existing Saturn V facilities at Launch Complex 39 to launch Saturn IB space vehicles. A launcher-umbilical tower would require a major modification, and minor modification would be required in the service platforms of the Vehicle Assembly Building, where space vehicles were assembled and checked out before being moved to the launch pad. The firm, fixed-price contract had a performance period of 200 days, with work to be performed at the Center and in Jacksonville.
MSFC issued a modification to an existing contract with McDonnell Douglas for Skylab Program work. The modification would pay for the conversion of the original OWS to be launched by a Saturn IB booster to a completely outfitted Workshop to be launched by a Saturn V. Originally the plan was to launch the second stage (S IVB) of a Saturn IB into Earth orbit. The S-IVB would be filled with fuel so that it could propel itself into orbit. Astronauts launched by a second Saturn IB would then rendezvous with the empty stage and convert it into living and working quarters. A decision was made 21 May 1969 to outfit an S-IVB on the ground and launch it ready for use on a Saturn V.
The Apollo 14 (AS-509) mission - manned by astronauts Alan B. Shepard, Jr., Stuart A. Roosa, and Edgar D. Mitchell - was launched from Pad A, Launch Complex 39, KSC, at 4:03 p.m. EST January 31 on a Saturn V launch vehicle. A 40-minute hold had been ordered 8 minutes before scheduled launch time because of unsatisfactory weather conditions, the first such delay in the Apollo program. Activities during earth orbit and translunar injection were similar to those of the previous lunar landing missions. However, during transposition and docking, CSM 110 Kitty Hawk had difficulty docking with LM-8 Antares. A hard dock was achieved on the sixth attempt at 9:00 p.m. EST, 1 hour 54 minutes later than planned. Other aspects of the translunar journey were normal and proceeded according to flight plan. A crew inspection of the probe and docking mechanism was televised during the coast toward the moon. The crew and ground personnel were unable to determine why the CSM and LM had failed to dock properly, but there was no indication that the systems would not work when used later in the flight.
Apollo 14 entered lunar orbit at 1:55 a.m. EST on February 4. At 2:41 a.m. the separated S-IVB stage and instrument unit struck the lunar surface 174 kilometers southeast of the planned impact point. The Apollo 12 seismometer, left on the moon in November 1969, registered the impact and continued to record vibrations for two hours.
After rechecking the systems in the LM, astronauts Shepard and Mitchell separated the LM from the CSM and descended to the lunar surface. The Antares landed on Fra Mauro at 4:17 a.m. EST February 5, 9 to 18 meters short of the planned landing point. The first EVA began at 9:53 a.m., after intermittent communications problems in the portable life support system had caused a 49-minute delay. The two astronauts collected a 19.5-kilogram contingency sample; deployed the TV, S-band antenna, American flag, and Solar Wind Composition experiment; photographed the LM, lunar surface, and experiments; deployed the Apollo lunar surface experiments package 152 meters west of the LM and the laser-ranging retroreflector 30 meters west of the ALSEP; and conducted an active seismic experiment, firing 13 thumper shots into the lunar surface.
A second EVA period began at 3:11 a.m. EST February 6. The two astronauts loaded the mobile equipment transporter (MET) - used for the first time - with photographic equipment, tools, and a lunar portable magnetometer. They made a geology traverse toward the rim of Cone Crater, collecting samples on the way. On their return, they adjusted the alignment of the ALSEP central station antenna in an effort to strengthen the signal received by the Manned Space Flight Network ground stations back on earth.
Just before reentering the LM, astronaut Shepard dropped a golf ball onto the lunar surface and on the third swing drove the ball 366 meters. The second EVA had lasted 4 hours 35 minutes, making a total EVA time for the mission of 9 hours 24 minutes. The Antares lifted off the moon with 43 kilograms of lunar samples at 1:48 p.m. EST February 6.
Meanwhile astronaut Roosa, orbiting the moon in the CSM, took astronomy and lunar photos, including photos of the proposed Descartes landing site for Apollo 16.
Ascent of the LM from the lunar surface, rendezvous, and docking with the CSM in orbit were performed as planned, with docking at 3:36 p.m. EST February 6. TV coverage of the rendezvous and docking maneuver was excellent. The two astronauts transferred from the LM to the CSM with samples, equipment, and film. The LM ascent stage was then jettisoned and intentionally crashed on the moon's surface at 7:46 p.m. The impact was recorded by the Apollo 12 and Apollo 14 ALSEPs.
The spacecraft was placed on its trajectory toward earth during the 34th lunar revolution. During transearth coast, four inflight technical demonstrations of equipment and processes in zero gravity were performed.
The CM and SM separated, the parachutes deployed, and other reentry events went as planned, and the Kitty Hawk splashed down in mid-Pacific at 4:05 p.m. EST February 9 about 7 kilometers from the recovery ship U.S.S. New Orleans. The Apollo 14 crew returned to Houston on February 12, where they remained in quarantine until February 26.
All primary mission objectives had been met. The mission had lasted 216 hours 40 minutes and was marked by the following achievements:
The 38.7-m-tall pedestal adapted to an existing launcher-umbilical tower so that manned Saturn IB space vehicles could be launched from facilities supporting the larger Saturn V rockets. Holloway contracted to construct the launcher- pedestal in 180 days after receiving notice to proceed.
The modification would extend IBM's delivery schedule for IUs through 31 December 1973, to be compatible with the extended Apollo and Skylab Program launch schedules. IBM was under NASA contract to build 27 IUs for Saturn vehicles: 12 Saturn IBs and 15 Saturn Vs. Ten of the Saturn IB units and 12 Saturn V units had been completed. All work was being done at the company's facilities in Huntsville. The original IU contract had been granted to IBM in March 1965 for the fabrication, assembly, checkout, and delivery of the 27 units and related support functions.
The modification would extend Boeing's integration work through 31 December 1972. The basic contract began in September 1964. Included in the modification was work on requirements for Saturn V vehicles that would launch the remaining Apollo lunar exploration missions (Apollo 15, 16, and 17) and the Skylab Program's Saturn Workshop. Boeing's systems engineering and integration work at the time of this modification award included requirements and documentation for presettings for onboard computers that determined launch events, propellant loadings for all three vehicle stages, vehicle structural integrity, expected heating environments, range safety, tracking and communication data, and postflight reconstruction of launch data. Boeing was also MSFC's contractor for manufacture and testing of the first (S IC) stage of the Saturn V.
Apollo 15 (AS-510) with astronauts David R. Scott, Alfred M. Worden, and James B. Irwin aboard was launched from Pad A, Launch Complex 39, KSC, at 9:34 a.m. EDT July 26. The spacecraft and S-IVB combination was placed in an earth parking orbit 11 minutes 44 seconds after liftoff. Activities during earth orbit and translunar injection (insertion into the trajectory for the moon) were similar to those of previous lunar landing missions. Translunar injection was at about 12:30 p.m., with separation of the CSM from the LM/S-IVB/IU at 12:56 p.m. At 1:08 p.m., onboard color TV showed the docking of the CSM with the LM.
S-IVB auxiliary propulsion system burns sent the S-IVB/IU stages toward the moon, where they impacted the lunar surface at 4:59 p.m. EDT July 29. The point of impact was 188 kilometers northeast of the Apollo 14 landing site and 355 kilometers northeast of the Apollo 12 site. The impact was detected by both the Apollo 12 and Apollo 14 seismometers, left on the moon in November 1969 and February 1971.
After the translunar coast, during which TV pictures of the CSM and LM interiors were shown and the LM communications and other systems were checked, Apollo 15 entered lunar orbit at 4:06 p.m. EDT July 29.
The LM-10 Falcon, with astronauts Scott and Irwin aboard, undocked and separated from the Endeavor (CSM 112) with astronaut Worden aboard. At 6:16 p.m. EDT July 30, the Falcon landed in the Hadley-Apennine region of the moon 600 meters north-northwest of the proposed target. About two hours later, following cabin depressurization, Scott performed a 33-minute standup EVA in the upper hatch of the LM, during which he described and photographed the landing site.
The first crew EVA on the lunar surface began at 9:04 a.m. July 31. The crew collected and stowed a contingency sample, unpacked the ALSEP and other experiments, and prepared the lunar roving vehicle (LRV) for operations. Some problems were encountered in the deployment and checkout of the LRV, used for the first time, but they were quickly resolved. The first EVA traverse was to the Apennine mountain front, after which the ALSEP was deployed and activated, and one probe of a Heat Flow experiment was emplaced. A second probe was not emplaced until EVA-2 because of drilling difficulties. The first EVA lasted 6 hours 33 minutes.
At 7:49 a.m. EDT August 1, the second EVA began. The astronauts made a maintenance check on the LRV and then began the second planned traverse of the mission. On completion of the traverse, Scott and Irwin completed the placement of heat flow experiment probes, collected a core sample, and deployed the American flag. They then stowed the sample container and the film in the LM, completing a second EVA of 7 hours 12 minutes.
The third EVA began at 4:52 a.m. August 2, included another traverse, and ended 4 hours 50 minutes later, for a total Apollo 15 lunar surface EVA time of 18 hours 35 minutes.
While the lunar module was on the moon, astronaut Worden completed 34 lunar orbits in the CSM operating scientific instrument module experiments and cameras to obtain data concerning the lunar surface and environment. X-ray spectrometer data indicated richer abundance of aluminum in the highlands, especially on the far side, but greater concentrations of magnesium in the maria.
Liftoff of the ascent stage of the LM, the first one to be televised, occurred at 1:11 p.m. EDT August 2. About two hours later the LM and CSM rendezvoused and docked, and film, equipment, and 77 kilograms of lunar samples were transferred from the LM to the CSM. The ascent stage was jettisoned and hit the lunar surface at 11:04 p.m. EDT August 2. Its impact was recorded by the Apollo 12, Apollo 14, and Apollo 15 seismometers, left on the moon during those missions. Before leaving the lunar orbit, the spacecraft deployed a subsatellite, at 4:13 p.m. August 4, in an orbit of 141.3 by 102 kilometers. The satellite would measure interplanetary and earth magnetic fields near the moon. It also carried charged-particle sensors and equipment to detect variations in lunar gravity caused by mascons (mass concentrations).
A transearth injection maneuver at 5:23 p.m. August 4 put the CSM on an earth trajectory. During the transearth coast, astronaut Worden performed an inflight EVA beginning at 11:32 a.m. August 5 and lasting for 38 minutes 12 seconds. He made three trips to the scientific instrument module (SIM) bay of the SM, twice to retrieve cassettes and once to observe the condition of the instruments in the SIM bay.
CM and SM separation, parachute deployment, and other reentry events went as planned, but one of the three main parachutes failed, causing a hard but safe landing. Splashdown - at 4:47 p.m. EDT August 7, after 12 days 7 hours 12 minutes from launch - was 530 kilometers north of Hawaii and 10 kilometers from the recovery ship U.S.S. Okinawa. The astronauts were carried to the ship by helicopter, and the CM was retrieved and placed on board. All primary mission objectives had been achieved. Additional Details: Apollo 15.
Released from Apollo 15 into lunar orbit on 4 August 1971; studied lunar particles and included fields experiments.
The Apollo 16 (AS-511) space vehicle was launched from Pad A, Launch Complex 39, KSC, at 12:54 p.m. EST April 16, with a crew of astronauts John W. Young, Thomas K. Mattingly II, and Charles M. Duke, Jr. After insertion into an earth parking orbit for spacecraft system checks, the spacecraft and the S-IVB stage were placed on a trajectory to the moon at 3:28 p.m. CSM transposition and docking with the LM were achieved, although a number of minor anomalies were noted.
One anomaly, an auxiliary propulsion system leak on the S-IVB stage, produced an unpredictable thrust and prevented a final S-IVB targeting maneuver after separation from the CSM. Tracking of the S-IVB ended at 4:04 p.m. EST April 17, when the instrument unit's signal was lost. The stage hit the lunar surface at 4:02 p.m. April 19, 260 kilometers northeast of the target point. The impact was detected by the seismometers left on the moon by the Apollo 12, 14, and 15 missions.
Spacecraft operations were near normal during the coast to the moon. Unexplained light-colored particles from the LM were investigated and identified as shredded thermal paint. Other activities during the translunar coast included a cislunar navigation exercise, ultraviolet photography of the earth and moon, an electrophoresis demonstration, and an investigation of the visual light-flash phenomenon noted on previous flights. Astronaut Duke counted 70 white, instantaneous light flashes that left no after-glow.
Apollo 16 entered a lunar orbit of 314 by 107.7 kilometers at 3:22 p.m. April 19. After separation of LM-11 Orion from CSM 112 Casper, a CSM active rendezvous kept the two vehicles close together while an anomaly discovered on the service propulsion system was evaluated. Tests and analyses showed the redundant system to be still safe and usable if required. The vehicles were again separated and the mission continued on a revised timeline because of the 5 3/4-hour delay.
The lunar module landed with Duke and Young in the moon's Descartes region, about 230 meters northwest of the planned target area at 9:23 p.m. EST April 20. A sleep period was scheduled before EVA.
The first extravehicular activity began at 11:59 a.m. April 21, after the eight-hour rest period. Television coverage of surface activity was delayed until the lunar roving vehicle systems were activated, because the steerable antenna on the lunar module could not be used. The lunar surface experiments packages were deployed, but accidental breaking of the electronics cable rendered the heat flow experiment inoperable. After completing activities at the experiments site, the crew drove the lunar roving vehicle west to Flag Crater, where they performed the planned tasks. The inbound traverse route was just slightly south of the outbound route, and the next stop was Spook Crater. The crew then returned via the experiment station to the lunar module and deployed the solar wind composition experiment. The duration of the extravehicular activity was 7 hours 11 minutes. The distance traveled by the lunar roving vehicle was 4.2 kilometers. The crew collected 20 kilograms of samples.
The second extravehicular traverse, which began at 11:33 a.m. April 22, was south-southeast to a mare-sampling area near the Cinco Craters on Stone Mountain. The crew then drove in a northwesterly direction, making stops near Stubby and Wreck Craters. The last leg of the traverse was north to the experiments station and the lunar module. The second extravehicular activity lasted 7 hours 23 minutes. The distance traveled by the lunar roving vehicle was 11.1 kilometers.
Four stations were deleted from the third extravehicular traverse, which began 30 minutes early at 10:27 a.m. April 23 to allow extra time. The first stop was North Ray Crater, where "House Rock" on the rim of the crater was sampled. The crew then drove southeast to "Shadow Rock." The return route to the LM retraced the outbound route. The third extravehicular activity lasted 5 hours 40 minutes, and the lunar roving vehicle traveled 11.4 kilometers.
Lunar surface activities outside the LM totaled 20 hours 15 minutes for the mission. The total distance traveled in the lunar roving vehicle was 26.7 kilometers. The crew remained on the lunar surface 71 hours 14 minutes and collected 96.6 kilograms of lunar samples.
While the lunar module crew was on the surface, Mattingly, orbiting the moon in the CSM, was obtaining photographs, measuring physical properties of the moon and deep space, and making visual observations. Essentially the same complement of instruments was used to gather data as was used on the Apollo 15 mission, but different areas of the lunar surface were flown over and more comprehensive deep space measurements were made, providing scientific data that could be used to validate findings from Apollo 15 as well as add to the total store of knowledge of the moon and its atmosphere, the solar system, and galactic space.
The LM lifted off from the moon at 8:26 p.m. EST April 23, rendezvoused with the CSM, and docked with it in orbit. Young and Duke transferred to the CSM with samples, film, and equipment, and the LM was jettisoned the next day. LM attitude control was lost at jettison; therefore a deorbit maneuver was not possible and the LM remained in lunar orbit, with an estimated orbital lifetime of about one year.
The particles and fields subsatellite was launched into lunar orbit and normal system operation was noted. However, the spacecraft orbital shaping maneuver was not performed before ejection and the subsatellite was placed in a non-optimum orbit that resulted in a much shorter lifetime than the planned year. Loss of all subsatellite tracking and telemetry data on the 425th revolution (May 29) indicated that the subsatellite had hit the lunar surface.
The mass spectrometer deployment boom stalled during a retract cycle and was jettisoned before transearth injection. The second plane-change maneuver and some orbital science photography were deleted so that transearth injection could be performed about 24 hours earlier than originally planned.
Activities during the transearth coast phase of the mission included photography for a contamination study for the Skylab program and completion of the visual light-flash-phenomenon investigation that had been partially accomplished during translunar coast. A 1-hour 24-minute transearth extravehicular activity was conducted by command module pilot Mattingly to retrieve the film cassettes from the scientific instrument module cameras, inspect the equipment, and expose a microbial-response experiment to the space environment. Two midcourse corrections were made on the return flight to achieve the desired entry interface conditions.
Entry and landing were normal, completing a 265-hour 51-minute mission. The command module was viewed on television while dropping on the drogue parachutes, and continuous coverage was provided through crew recovery. Splashdown was at 2:44 p.m. EST April 27 in mid-Pacific, 5 kilometers from the recovery ship U.S.S. Ticonderoga. All primary mission objectives had been achieved. Additional Details: Apollo 16.
Released from Apollo 16 into lunar orbit on 24 April 1972; fields and particles data; impacted lunar surface.
Apollo 17 (AS-512), the final Apollo manned lunar landing mission, was launched from Pad A, Launch Complex 39, KSC, at 12:33 a.m. EST December 7. Crew members were astronauts Eugene A. Cernan, Ronald E. Evans, and Harrison H. Schmitt. The launch had been delayed 2 hours 40 minutes by a countdown sequencer failure, the only such delay in the Apollo program caused by a hardware failure.
All launch vehicle systems performed normally in achieving an earth parking orbit of 170 by 168 kilometers. After checkout, insertion into a lunar trajectory was begun at 3:46 a.m.; translunar coast time was shortened to compensate for the launch delay. CSM 114 transposition, docking with LM-12, and LM ejection from the launch vehicle stage were normal. The S-IVB stage was maneuvered for lunar impact, striking the surface about 13.5 kilometers from the preplanned point at 3:27 p.m. EST December 10. The impact was recorded by the passive seismometers left on the moon by Apollo 12, 14, 15, and 16.
The crew performed a heat flow and convection demonstration and an Apollo light-flash experiment during the translunar coast. The scientific instrument module door on the SM was jettisoned at 10:17 a.m. EST December 10. The lunar orbit insertion maneuver was begun at 2:47 p.m. and the Apollo 17 spacecraft entered a lunar orbit of 315 by 97 kilometers. After separation of the LM Challenger from the CSM America and a readjustment of orbits, the LM began its powered descent and landed on the lunar surface in the Taurus-Littrow region at 2:55 p.m. EST on December 11, with Cernan and Schmitt.
The first EVA began about 4 hours later (6:55 p.m.). Offloading of the lunar roving vehicle and equipment proceeded as scheduled. The Apollo Lunar Surface Experiment Package was deployed approximately 185 meters west northwest of the Challenger. Astronaut Cernan drove the lunar roving vehicle to the experiments deployment site, drilled the heat flow and deep core holes, and emplaced the neutron probe experiment. Two geological units were sampled, two explosive packages deployed, and seven traverse gravimeter measurements were taken. During the 7-hour 12-minute EVA, 14 kilograms of samples were collected.
The second extravehicular activity began at 6:28 p.m. EST December 12. Because of geological interest, station stop times were modified. Orange soil was discovered and became the subject of considerable geological discussion. Five surface samples and a double core sample were taken in the area of the orange soil. Three explosive packages were deployed, seven traverse gravimeter measurements were taken, and observations were photographed. Samples collected totaled 34 kilograms during the 7 hours and 37 minutes of the second EVA.
The third and final EVA began at 5:26 p.m. EST December 13. Specific sampling objectives were accomplished. Samples - including blue-gray breccias, fine-grained vesicular basalts, crushed anorthositic rocks, and soils - weighed 66 kilograms. Nine traverse gravimeter measurements were made. The surface electrical properties experiment was terminated. Before reentering the LM, the crew selected a breccia rock to dedicate to the nations represented by students visiting the Mission Control Center. A plaque on the landing gear of the lunar module, commemorating all of the Apollo lunar landings, was then unveiled. After 7 hours 15 minutes, the last Apollo EVA on the lunar surface ended. Total time of the three EVAs was approximately 22 hours; the lunar roving vehicle was driven 35 kilometers, and about 115 kilograms of lunar sample material was acquired.
While Cernan and Schmitt were exploring the lunar surface, Evans was conducting numerous scientific activities in the CSM in lunar orbit. In addition to the panoramic camera, the mapping camera, and the laser altimeter, three new scientific instrument module experiments were included in the Apollo 17 orbital science equipment. An ultraviolet spectrometer measured lunar atmospheric density and composition; an infrared radiometer mapped the thermal characteristics of the moon; and a lunar sounder acquired data on the subsurface structure.
Challenger lifted off the moon at 5:55 p.m. EST December 14. Rendezvous with the orbiting CSM and docking were normal. The two astronauts transferred to the CM with samples and equipment and the LM ascent stage was jettisoned at 1:31 a.m. December 15. Its impact on the lunar surface about 1.6 kilometers from the planned target was recorded by four Apollo 17 geophones and the Apollo 12, 14, 15, and 16 seismometers emplaced on the surface. The seismic experiment explosive packages that had been deployed on the moon were detonated as planned and recorded on the geophones.
During the coast back to earth, Evans left the CSM at 3:27 p.m. EST December 17 for a 1-hour 7-minute inflight EVA and retrieved lunar sounder film and panoramic and mapping camera cassettes from the scientific instrument module bay. The crew conducted the Apollo light- flash experiment and operated the infrared radiometer and ultraviolet spectrometer.
Reentry, landing, and recovery were normal. The command module parachuted into the mid-Pacific at 2:25 p.m. EST December 19, 6.4 kilometers from the prime recovery ship, U.S.S. Ticonderoga. The crew was picked up by helicopter and was on board the U.S.S. Ticonderoga 52 minutes after the CM landed. All primary mission objectives had been achieved. Additional Details: Apollo 17.
MSFC began implementation of a plan for preparation and storage of unassigned Saturn hardware, phaseout of the Saturn V production capability, and amendment of the facility operations contract at the Michoud Assembly Facility for minimum surveillance of stored hardware.
First and only US space station to date. Project began life as Apollo Orbital Workshop - outfitting of an S-IVB stage with docking adapter with equipment launched by several subsequent S-1B launches. Curtailment of the Apollo moon landings meant that surplus Saturn V's were available, so the pre-equipped, five times heavier, and much more capable Skylab resulted.
An unexpected telemetry indication of meteoroid shield deployment and solar array wing 2 beam fairing separation was received 1 minute and 3 seconds after liftoff. However, all other systems of the OWS appeared normal, and the OWS was inserted into a near-circular Earth orbit of approximately 435 km altitude. The payload shroud was jettisoned, and the ATM with its solar array was deployed as planned during the first orbit. Deployment of the Workshop solar array and the meteoroid shield was not successful. In fact the xternal solar/meteoroid shield had ripped off 63 seconds into ascent, tearing away one solar panel wing and debris jamming the remaining panel. Without shield temperatures soared in station. Repairs by crews led to virtually all mission objectives being met.
Following the final manned phase of the Skylab mission, ground controllers performed some engineering tests of certain Skylab systems--tests that ground personnel were reluctant to do while men were aboard. Results from these tests helped to determine causes of failures during the mission and to obtain data on long term degradation of space systems.
Upon completion of the engineering tests, Skylab was positioned into a stable attitude and systems were shut down. It was expected that Skylab would remain in orbit eight to ten years. It was to have been visited by an early shuttle mission, reboosted into a higher orbit, and used by space shuttle crews. But delays in the first flight of the shuttle made this impossible.
On July 11, 1979, Skylab disintegrated when it re-entered the earth's atmosphere after a worldwide scare over its pending crash. The debris stretched from the south-east Indian Ocean into Western Australia. Additional Details: Skylab 1.
Guidelines were issued by NASA Hq for release, disposition, and storage of all unneeded Skylab Program equipment. Two Saturn Vs, two Saturn IBs, three command and service modules, the backup Skylab cluster, and appropriate spares would be placed in minimum cost storage as soon as program requirements permitted.
MSFC published a summary of Skylab operations. Additional Details: Summary of Skylab operations..
NASA realized that after the completion of the Apollo, Skylab, and ASTP programs there would still be significant Apollo surplus hardware. This amounted to two Saturn V and three Saturn IB boosters; one Skylab space station, three Apollo CSM's and two Lunar Modules. After many iterations NASA considered use of these assets for a second Skylab station in May 1973. A range of options were considered. Saturn V SA-515 would boost the backup Skylab station into orbit somewhere between January 1975 and April 1976. It would serve as a space station for Apollo and Soyuz spacecraft in the context of the Apollo ASTP mission. The Advanced or International Skylab variants proposed use of Saturn V SA-514 to launch a second workshop module and international payloads. This station would be serviced first by Apollo and Soyuz, then by the space shuttle. Using the existing hardware, these options would cost anywhere from $ 220 to $ 650 million. But funds were not forthcoming. The decision was taken to mothball surplus hardware in August 1973. In December 1976, the boosters and spacecraft were handed over to museums. The opportunity to launch an International Space Station, at a tenth of the cost and twenty years earlier, was lost.