In the first half of the 1960's it was planned to make suborbital tests of nuclear propulsion for upper stages using a Saturn IB first stage to boost a Rover-reactor powered second stage on a suborbital trajectory. The second stage would impact the Atlantic Ocean down range from Cape Canaveral.
Liftoff Thrust: 682,200 kgf. Total Mass: 625,000 kg. Core Diameter: 6.5 m. Total Length: 80.0 m.
At the suggestion of Theodore von Kármán and following a request of Gen. H. B. Thatcher, an Ad Hoc Committee of the Scientific Advisory Board met in the Pentagon to consider the application of nuclear energy to missile propulsion. In its report, the Committee "noted that there was an almost complete hiatus in the study of the nuclear rocket from 1947 following a report by North American Aviation, until a 1953 report by the Oak Ridge National Laboratory. Because the technical problems appear so severe, and because another 6 years of no progress in this area would seem to be unfortunate," the Committee felt that a continuing study both analytical and experimental, at a modest level of effort, should be carried on.
NACA Lewis Laboratory presented ARDC with results of air-breathing nuclear propulsion systems for manned applications, leading to AEC-AF Pluto project, and also initiated comparison of nuclear rocket with chemical systems for ICBM, a concept of use to Rover program.
The Atomic Energy Commission approved, on the basis of a statement of interest by the Department of Defense, the proposed plans of the Los Alamos Scientific and the Radiation Laboratories of the University of California, for the study and development of nuclear power for rocket propulsion.
As a result of guidance from the Secretary of Defense as to desired level of effort, the Atomic Energy Commission reduced its program on nuclear rocket propulsion to a single laboratory effort, phasing out work at the University of California Radiation Laboratory and concentrating AEC development efforts at Los Alamos Scientific Laboratory.
Research on tungsten nuclear rocket propulsion systems initiated by NACA Lewis Laboratory, and other feasible systems for practical nuclear rocket systems, such as 1958 concept of coaxial jet gaseous reactor, followed.
The first experimental reactor (Kiwi-A) in the nuclear space rocket program operated successfully at full temperature and duration at Jackass Flats, Nev.
The Chairman, AEC, in a letter to the Administrator of NASA, proposed a flight test objective be established for the nuclear rocket program and proposed a technical program and division of agency responsibilities to achieve those objectives.
The House Committee on Science and Astronautics declared: "A high priority program should be undertaken to place a manned expedition on the moon in this decade. A firm plan with this goal in view should be drawn up and submitted to the Congress by NASA. Such a plan, however, should be completely integrated with other goals, to minimize total costs. The modular concept deserves close study. Particular attention should be paid immediately to long lead-time phases of such a program." The Committee also recommended that development of the F-1 engine be expedited in expectation of the Nova launch vehicle, that there be more research on nuclear engines and less conventional engines before freezing the Nova concept, and that the Orion project be turned over to NASA. It was the view of the Committee that "NASA's 10-year program is a good program, as far as it goes, but it does not go far enough. Furthermore the space program is not being pushed with sufficient energy."
Second experimental reactor (Kiwi-A Prime) in the Project Rover nuclear rocket program was successfully tested at full power and duration at Jackass Flats, Nev.
The third meeting of the Space Exploration Program Council was held at NASA Headquarters. The question of a speedup of Saturn C-2 production and the possibility of using nuclear upper stages with the Saturn booster were discussed. The Office of Launch Vehicle Programs would plan a study on the merits of using nuclear propulsion for some of NASA's more sophisticated missions. If the study substantiated such a need, the amount of in-house basic research could then be determined.
In a memorandum to NASA Associate Administrator Robert C. Seamans, Jr., Robert L. King, Executive Secretary, described the action taken on certain items discussed at the July 14-15 meeting of the Space Exploration Program Council. Among these actions was the awarding of a contract to The RAND Corporation to evaluate missions for which nuclear propulsion would be desirable. Included in the study would be the determination of availability dates, cost of development, operational costs, the safety aspects of the missions, and an evaluation of research requirements.
AEC briefing held at the Nevada Test Site at Jackass Flats, Nev., for representatives of 26 companies for proposals to study the requirements for a National Nuclear Rocket Engine Development Facility. Existing test facilities are fully committed to the development of nuclear reactors.
Kiwi-A No. 3 static test of nuclear rocket propulsion was successfully conducted at AEC Nevada test site, resulting in NASA-AEC call for bids for industrial development phase of Project Rover on November 1, 1960.
NASA-AEC Space Nuclear Propulsion Office invited industry to submit proposals for participation in development of Nerva (nuclear engine for rocket vehicle application), a part of Project Rover initiated in 1955 by USAF-AEC.
Reactor-in-flight-test system (Rift) study, a part of the NASA-AEC program on nuclear rockets, was briefed by contractors at NASA headquarters.
NASA Associate Administrator Robert C. Seamans, Jr., established the Ad Hoc Task Group for a Manned Lunar Landing Study, to be chaired by William A. Fleming of NASA Headquarters. The study was expected to produce the following information:
The engineering sketch drawn by John D. Bird of Langley Research Center on May 3, 1961, indicated the thinking of that period: By launching two Saturn C-2's, the lunar landing mission could be accomplished by using both earth rendezvous and lunar rendezvous at various stages of the mission.
Following Gagarin's flight and Bay of Pigs failure, Kennedy announces the objective of landing an American on the moon by end of the decade. In his second State of the Union Message President Kennedy said: "With the advice of the Vice President, who is Chairman of the National Space Council, we have examined where we (United States) are strong and where we are not, where we may succeed and where we may not. . . . Now is the time to take longer strides-time for a great new American enterprise-time for this Nation to take a clearly leading role in space achievement which in many ways may hold the key to our future on Earth." President Kennedy set forth an accelerated space program based upon the long-range national goals of landing a man on the Moon and returning him safely to Earth; early development of the Rover nuclear rocket; speed up the use of Earth satellites for worldwide communications; and provide "at the earliest possible time a satellite system for worldwide weather observation." An additional $549 million was requested for NASA over the new administration March budget requests; $62 million was requested for DOD for starting development of a solid-propellant booster of the Nova class.
NASA selected Vitro Engineering Co. for negotiation of a design contract for an engine maintenance and disassembly building, one of the facilities to be a part of the National Nuclear Rocket Development Center.
Power run completed the test series on the Kiwi B-1A reactor system being conducted at the Nevada Test Site by AEC's Los Alamos Scientific Laboratory. Fourth in a series of test reactors in the joint AEC-NASA nuclear rocket propulsion program, Kiwi B-1A was disassembled for examination at the conclusion of the test runs.
NASA selected Mason-Rust as the contractor to provide support services at NASA's Michoud plant near New Orleans, providing housekeeping services through June 30, 1962 for the three contractors who would produce the Saturn S-I and S-IB boosters and the Rift nuclear upper-stage vehicle.