This page no longer updated from 31 October 2001. Latest version can be found at www.astronautix.com
 |
LK-700 Appearance of the LK-700 spacecraft at each phase of its direct lunar landing mission.Credit: © Mark Wade. 28,517 bytes. 640 x 331 pixels. |
Class: Manned. Type: Lunar Lander. Nation: USSR. Manufacturer: OKB-52. Chelomei's TsKBM began work on the UR-700 launch vehicle for manned lunar landing missions in 1962. Variants were studied with 70 to 175 tonnes payload, and rocket stages of various thrust levels, including nuclear stages. The conclusion was reached that a direct lunar landing would require a payload of 130 to 170 tonnes. Initial LK-700 spacecraft designs were derived from the 'Raketoplan' family of manned modular space vehicles. Although Korolev's N1-L3 design was selected in 1964 for the manned lunar landing, the project quickly encountered delays and weight growth. A revised UR-700/LK-700 design was presented on 16 November 1966 to an expert commission headed by Keldysh as an alternative to Korolev/Mishin's N1-L3 lunar lander project. Although Chelomei had lined up the support of Glushko, and Mishin was in a weak position after Korolev's death, Keldysh managed to ensure that the N1-L3 continued. However continued design work on the LK-700, the UR-700 booster, and development of the RD-270 engine were authorised. Chelomei took a sound conservative design approach (i.e. no docking required, no cryogenics) with the capability for evolutionary later improvement (propellant utilisation system, 'hot' backup engines). The design directive documents were signed by Chelomei on 21 July 1967.
Development of the LK-700 manned lunar landing spacecraft was undertaken in accordance with decree 1070-363 of the Soviet Ministers and Central Committee of the Communist Party on 17 September 1967 and MOM decree 472 of 28 September 1967. Study index number 4855CC by TsNIIMASH in 1966 showed that any development of improved versions of the N1 would be practically equivalent to design and qualification of a new rocket, while the UR-700 modular approach allowed a range of payloads without requalification. The UR-700/LK-700 combination could support the DLB lunar base better, as well as Venus/Mars manned flybys and Mars landing expeditions.
It was planned that a total of 16 prototype articles of the LK-700 would be built for: component qualification test, dimensional fit test, static test, functional mock-up, ECS test, thermal test, module interface test, landing gear trials, antenna deployment test, SAS launch escape system test, impact and sea recovery trials, engine test, heat shield trials, and crew training.
 | LK-700 Spacecraft - LK-700 Spacecraft with landing stage and landing gear deployed. Credit: © Mark Wade. 11,508 bytes. 350 x 233 pixels. |
A total of five ship-sets of UK-700/LK-700 flight articles were to be built. Two unmanned flights were to be followed by three manned flights.
Project plan was as follows:
- October-November 1968: Beginning of serious engineering work requiring external financing
- October 1968 to January 1973: Engineering design and drawing release
- 2nd Quarter 1969: Selection of cosmonaut training group
- 4th Quarter 1969: Completion of prototype article design
- 2nd Quarter 1970: Completion of flight article design
- Beginning 1971: Completion of LK-700 prototype tests
- April 1971 to April 1973: Flight crew training
- November 1971: Delivery of first LK-700 fight article. Subsequent deliveries in April, July, October 1972 and January 1973
- October 1971: Delivery of first UR-700 launch vehicle. Subsequent deliveries n February, May, August, November 1972.
- May 1972: First UR-700/LK-700 unmanned launch. Subsequent unmanned launches in November 1972 and April 1973
- April 1973: First manned UR-700/LK-700 launch. Subsequent manned flights in August and October 1973.
To support development of the LK-700, a range of research would be required to characterise cis-lunar space:
- Dosimetric measurements of space radiation
- Micrometeoroid environment
- Solar and cosmic radiation
- Surveys of the lunar surface, including landing site selection, development of a selenographic co-ordinate system, establishment of navigation parameters
- Measurement of the magnetic field of the moon
- Mineralogical survey of the surface
- Passive seismic observations
- Lunar surface temperatures
- Gravitational field measurement and variations
- Solar plasma
- Televised scientific observations
- Gamma spectrometer reading of the chemical composition of the surface
- Residual magnetic pole
- Laser reflector position observations
The draft project selected a preferred launch vehicle configuration using RD-270 engines, delivering 150 tonnes in low earth orbit, which could place two cosmonauts on any point of 88% of the visible lunar surface. The crew would spend one day on the surface, with the return trajectory taking 3.5 to 6.5 days depending on the landing site. The preferred landing site was in the Sea of Fertility or Ocean of Storms, which allowed the best angle of intersection of the hyperbolic departure trajectory with the lunar surface, requiring the minimum rearrangement of internal systems.
 | UR-700 - UR-700 Launch Vehicle for Direct Lunar Landing Mission Credit: © Mark Wade. 14,338 bytes. 128 x 480 pixels. |
Following initial LK-700 landings the LKE Lunar Expeditionary Complex would be delivered to the surface. This would permit long duration investigations of the surface and a much wider range of research. Precision landings in support of the LKE and lunar base would use Ye-8 Lunokhods equipped with radio homing beacons. The complex would be delivered in two to three UR-700 launches:
- Launch 1: Heavy Unpiloted Station - a one-way flight to deliver a __ tonne lunar station to the surface.
- Launch 2: LK-700 spacecraft with crew. The LK-700 would provide return transportation and was capable of being placed in dormant mode for a month.
- Launch 3: Lunar laboratory / Heavy Lunokhod would be landed to provide mobility for surface expeditions.
Three to six months of operations would be conducted on the lunar surface. It was recommended that a reserve LK-700 lander be standing ready for launch in case of emergencies or stranding of the crew on the surface.
The later DLB lunar base would require 80 tonnes per year of payload delivered to the surface starting in 1975, followed by 150 tonnes per year after 1980. Versions of the UR-700/LK-700 could handle this more easily than modifying the N1.
Lunar versions of the Almaz OPS would be placed in lunar orbit to conduct detailed reconnaissance of the surface using manned assistance. The OPS would also be used as a command post to co-ordinate the work of lunar surface operations and organise rescues in the case of emergencies on the surface.
Although mock-ups were built, no financing for full scale development was forthcoming by the required October 1968 date. By then it was apparent, that barring some disaster with an Apollo spacecraft, the moon race was lost. Kremlin interest in supporting such projects waned.
Following the explosion of the first N1 in January 1969, Pilyugin was called to a meeting at the Kremlin. Chelomei was again proposing the use of his UR-700/LK-700 in the place of the N1-L3, and a flight to Mars using an even larger version of the launch vehicle. Afanasyev was preparing a decree along these lines. Pilyugin refused to participate in this 'adventure'.
Nevertheless Chelomei's bureau continued to study the design until 1974, when the project was finally and definitively suppressed with the cancellation of the N1 and the lunar base projects.
 | UR-700 Cutaway - UR-700 lunar landing launch vehicle - From left: cutaway and bottom views; cutaway of core vehicle after six external stage one modules and shrouds were jettisoned; external view. The cutaway shows the arrangement of N2O4 oxidiser tanks (green) and UDMH fuel tanks (orange). The six outer 4.1 m diameter modules contained fuel and oxidizer tanks for stage 1 and fuel or oxidiser tanks for the three core modules. After propellant depletion, the six outer modules would separate, leaving the three core modules to continue their burn. The third stage, based on the Proton first stage, placed the LK-700 spacecraft into a 200 km earth orbit. The LK-700 was equipped with four nearly identical clustered stages and a lunar landing/ascent stage. The three outer stages fired to place the spacecraft on a translunar trajectory. The inner core stage was used for midcourse corrections, braked the spacecraft into lunar orbit, and then again until it was just above the lunar surface. The ascent stage performed the final soft landing on the moon and then, using the landing legs as a launch platform, launched the LK-700 capsule back towards the earth. Credit: © Mark Wade. 38,472 bytes. 471 x 600 pixels. |
Technical Description
The RKS Rocket-Space System was designed for direct landing on the moon without docking in earth or lunar orbit. It consisted of:
- LK-700 spacecraft
- UR-700 launch vehicle
- Launch complex for the UR-700
- Technical positions which would take factory-completed modules and conduct assembly and check-out operations before moving them to the pad for launch
- Command-tracking system
- Crew landing and rescue system
- Crew recovery system
Chief Designer Vladimir Chelomei felt that the lunar orbit rendezvous approach of Korolev's N1-L3 system compromised crew safety to an unacceptable degree. The fact that there was no backup method of return to the earth after the LK separated from the LOK lunar orbiter was particularly troubling. For this reason he favoured the 'direct landing' approach. The LK-700 was also a universal spacecraft suitable for other applications beyond the landing on the surface. The principles of its design were:
- The direct landing scheme would allow development of a simpler and more reliable lunar expedition system, while allowing landings at any point over 88% of the visible surface of the moon and a much wider launch window for a given mission energy. No docking was required. The N1-L3 / Apollo lunar orbit rendezvous technique limited sustained lunar surface operations to a small region around the lunar equator (due to the one month lunar period of rotation, other locations would have to wait two weeks before the companion spacecraft in lunar orbit came over the landing site again).
- N2O4 / UDMH storable propellants used universally in all stages of the launch vehicle and spacecraft.
- High reliability would be obtained in all portions of the system by minimising the number of parts.
- Earliest possible date for the landing would be achieved by using proven systems, requiring a minimum of new hardware development. Minimum modifications of existing UR-100 and UR-500 engines were used in the upper stages. Use of the same equipment in all stages of the launch vehicle and spacecraft wherever possible.
- Crew of no less than two for the initial mission in order to provide mutual support during lunar surface operations. A crew of three would be possible on later missions after a better launch vehicle propellant utilisation system was put into operation.
 | UR-700 Profile - UR-700 Launch Profile. At liftoff, nine engines - six on the six outer stage 1 modules, and three on the three core modules - fired. During the stage 1 burn, the three engines of the core modules were fed by propellants in forward tanks of the outer six modules. Therefore the Stage 2 core burn started with full tanks in the core modules. Stage 3, a modification of the Proton first stage, placed the 151 tonne LK-700 spacecraft into a 200 km earth parking orbit. Credit: © Mark Wade. 28,559 bytes. 582 x 271 pixels. |
- All elements of the system would be completed, tested, and certified flight ready in the factory before being shipped to the launch site. No requirement for construction facilities at the launch site.
- The design would have reserve capacity to allow a range of propellant loading. This meant that a wider range of launch windows, landing sites, and flight trajectories would be available without having to redesign the launch vehicle and spacecraft. Later a wider range of landing points, return times, and so on were possible by a heavier vehicle (with completely fuelled tanks) or by adding propellant cross-feed features (topping up the central ascent stage tank with residual propellant from the lateral landing stage tanks).
- Safety of the crew was assured throughout the mission through use of double or triple redundant systems and the use of the next rocket stage in the series for manoeuvres in case of the failure of a lower stage
- The complex could be easily adapted for a wide range of missions. For example, the launch vehicle payload could be increased by stretching the propellant tanks. This would allow addition of an airlock and lunar surface shelter to the lander for extended exploration missions. Other possibilities were a stretched re-entry capsule for increased number of crew, and transport variants.
The total mass of the LK-700 in low earth orbit was 154,000 kg for the Sea of Fertility mission. The spacecraft had a total length of 21.2 m with the ADU abort system and the spacecraft and stages had a basic diameter of 2.7 m. The components were:
- Block 1 Translunar Injection Stage: This consisted of three identical stages clustered around the core. Total mass of 103,474 kg (three rocket stages of 34,491 kg each). Each stage was equipped with a 23,500 tonne thrust Kosberg 11D23 engine.
- Block 11 Midcourse manoeuvre/lunar braking stage: Mass 32,226 kg (similar to the three Translunar injection stages clustered around it). 2,041 kg of propellant used for mid-course corrections prior to the start of the lunar braking manoeuvre. The remainder of the propellants were used to brake the spacecraft to 30 m/s at 4.3 km above the lunar surface, at which point this stage was jettisoned. This stage differed from the lateral Block 1 stages in having an engine unit for orientation of the assembly. It was equipped with a single Kosberg 11D23 main engine of 23.5 tonnes thrust, surrounded by three Isayev 11D416 engines of 1.67 tonnes thrust for midcourse manoeuvres and orientation of the spacecraft during the braking manoeuvre.
- Block 111 Soft Landing Stage: Mass 3500 kg. The unique soft landing platform consisted of six landing gear, each equipped with long ski-like landing pads. This design could accommodate safe landings at vertical velocities of up to 5 m/s; lateral velocities of 2 m/s; and provide a level launch platform on 15 degree slopes. Before launch of the ascent stage special electric devices in each gear would level the platform.
- Block 1V Trans-earth injection / midcourse manoeuvre stage:: 11,670 kg (mass 2,675 kg without propellant). This stage, using the Block 11 as a launch platform, launched the VA return capsule onto the trans-earth trajectory. It also contained spacecraft avionics and life support systems not in the VA re-entry capsule. It was equipped with a single Isotov (Klimov) 15D13 main engine of 13.4 tonnes thrust, surrounded by three Isayev 11D416 engines of 1.67 tonnes thrust for soft landing on the moon and midcourse manoeuvres.
- Block V VA Re-entry Capsule: Mass 3,130 kg. This 'gumdrop' Apollo-shaped capsule was similar to that developed by Chelomei for the LK-1 translunar spacecraft and TKS manned ferry. With a hypersonic lift to drag ratio of 0.35 the capsule could manoeuvre during re-entry at 11 km/ s to a landing on Soviet territory. Within the VA were the crew cabin, the drogue and main parachute systems, reaction control system for stabilising the spacecraft during re-entry, and a separable heat shield. Two lunar spacesuits were stored in the cabin for donning prior to moonwalks. The cabin could be depressurised for two to four hours at a time. On the nose of the VA was a parabolic antenna for communications, television transmission to earth, and high rate telemetry transmission.
- Block V1 ADU abort tower. This solid propellant launch escape tower was available from 1.5 hours before launch to 193 seconds into the flight to pull the VA capsule away from the launch vehicle in case of a booster failure. During the first 120 seconds of flight, the ADU would pull the VA away from the booster without its heat shield. From 120 to 193 seconds, the heat shield would remain attached to the VA. At 193 seconds into the flight four explosive bolts separated the ADU from the VA and small solid rocket motors pulled it away from the booster. Thereafter aborts would use the LK-700's Block 1V engine. The abort system was developed by NIITI.
The mission profile for the typical Sea of Fertility 8.3 day mission with a crew of 2 was:
- Insertion of the 154,000 kg spacecraft into a 186 x 260 km earth parking orbit, orbital inclination 51.5 degrees. Five hours (3.75 revolutions) would be spent in parking orbit before the translunar injection manoeuvre. During this time the crew check out all systems, including the radio altimeter for the critical lunar landing manoeuvre. The KIK tracking stations conduct precision tracking to refine the orbit of the spacecraft and the data is uploaded to the spacecraft navigation system, which includes a gyroscopic platform and a stellar orientation system. The restartable orientation engines of the Block 11 stage provide orientation and ullage for starting of the Block 1 stage. 3,000 kg of consumables are used during the parking orbit phase.
- Translunar injection manoeuvre of 3,170 to 3,185 m/s delta v. The starting mass of the spacecraft is 151,000 kg. After translunar injection, the three lateral stages of the Block 1 are jettisoned.
- Spacecraft mass now 50,526 kg. 2,041 kg of propellant and consumables are used in spacecraft orientation and two midcourse correction manoeuvres during the 3.32 day coast to moon (coast time 6.3 days for an Ocean of Storms mission). The spacecraft is tracked from KIP stations in Yevpatoriya, Shchelkov, Ussuriysk, and Sary Shagan, for six to fourteen hours each day.
- Begin lunar braking manoeuvre using the Block 11 stage at an altitude of 200 to 500 km (depending on the landing site) above the lunar surface. Mass of spacecraft 48,485 kg at start of manoeuvre. The Block 11's 11D23 engine shuts down when the radio altimeter indicates velocity of 30 m/s at 4.3 km above the surface. The Block 11 stage is jettisoned.
- The 11D416 engine of the LK-700 Block 111 lander stage ignites 4.3 km plus or minus 1 km above the lunar surface. Mass of the spacecraft is now 18,300 kg. 1176 kg of propellant are allocated for the final soft landing manoeuvre of about 120 seconds duration. During the manoeuvre the radio altimeter system is used to throttle the engine and keep the centre of mass of the spacecraft on the vertical. Mass landed on the moon 17,124 kg.
- Immediately after landing the crew checks out the spacecraft's systems and determine the precise position of the landing. The crew spends 12 to 24 hours on the surface, conducting two moonwalks of 2 to 2.5 hours duration each. On the surface scientific instruments are set up. 10 kg of lunar soil and movie film of the expedition are to be returned to earth with the crew.
- Trans-earth injection is conducted directly from the lunar surface, using the landing gear of the 3,500 kg Block 111 as a launch stand. The Block 1V stage's ascent manoeuvre consists of 4 to 6 seconds vertical ascent at maximum thrust, followed by throttle-back; a further and 8 to 25 seconds (depending on landing site) of vertical climb; followed by a pitch-over to the velocity vector required for the return to earth. Total delta v is 2,740 to 2,840 m/s. Mass of the spacecraft on trans-earth trajectory is 5,805 kg. 4.0 days is spent on the earth return trajectory with two midcourse corrections planned.
- Re-entry into earth's atmosphere is on a hyperbolic trajectory with perigee of 50 km. The radio altimeter comes into service again to update the spacecraft's position from 1,000 km to 250 km above the earth. The Block 1V stage separates at 150 km altitude after orienting the VA capsule at the correct angle for re-entry into the atmosphere at 100 km altitude. The VA uses its hypersonic lift to drag ratio of 0.35 to limit G-forces on the crew during re-entry. The lift allows it to vary its landing point from 6,000 to 11,000 km from the atmosphere entry point and from 300 km to the left or right of the ballistic course.
SpecificationCraft.Crew Size: 2. Design Life: 14 days. Orbital Storage: 45.00 days. Total Length: 21.2 m. Maximum Diameter: 2.7 m. Total Mass: 154,000 kg. Primary Engine Thrust: 13,400 kgf. Main Engine Propellants: N2O4/UDMH. Main Engine Isp: 326 sec. Total spacecraft delta v: 9,061 m/s.
- Module: Block 1. Purpose: Translunar Injection Stage. Overall Mass: 103,474 kg. Maneuver System Thrust: 70,500 kgf. Maneuver System Propellants: N2O4/UDMH. Maneuver System Isp: 326 sec. Maneuver system delta v: 3,185 m/s. Remarks: Three identical stages of 34,491 kg each clustered around the core.
- Module: Block 11. Purpose: Midcourse manoeuvre/lunar braking stage. Overall Mass: 32,226 kg. RCS Propellants: N2O4/UDMH. Maneuver System Thrust: 28,510 kgf. Maneuver System Propellants: N2O4/UDMH. Maneuver System Isp: 326 sec. Maneuver system delta v: 3,000 m/s. Remarks: Differed from the lateral Block 1 stages in having an engine unit for orientation of the assembly. Main engine of 23,500 kgf and three engines for soft landing / midcourse maneuvers of 1,670 kgf each.
- Module: Block 111. Purpose: Soft Landing Stage. Overall Mass: 3,500 kg. RCS Propellants: N2O4/UDMH.
- Module: Block 1V. Purpose: Trans-earth injection / midcourse manoeuvre stage. Overall Mass: 11,670 kg. Propellants: 8995 RCS Propellants: N2O4/UDMH. Maneuver System Thrust: 18,410 kgf. Maneuver System Propellants: N2O4/UDMH. Maneuver system delta v: 2,804 m/s. Remarks: Main engine of 13,400 kgf and three engines for soft landing / midcourse maneuvers of 1,670 kgf each.
- Module: Block V. Purpose: VA Re-entry Capsule. Modules.Crew Size: 2. Length: 2.5 m. Basic Diameter: 2.7 m. Max Diameter: 2.7 m. Habitable Volume: 4.00 m3. Overall Mass: 3,130 kg. RCS Propellants: N2O4/UDMH. L/D Hypersonic: 0.35.
LK-700 Chronology
01 January 1962
UR-700 launch vehicle for manned lunar landing missions. Launch Vehicle: UR-700. Chelomei's TsKBM began work on the UR-700. The conclusion was reached that a direct lunar landing would require a payload of 130 to 170 tonnes. Initial LK-700 spacecraft designs were derived from the 'Raketoplan' family of manned modular space vehicles. Korolev's N1-L3 design was selected in 1964 for the manned lunar landing, but the UR-700 would surface again when the N1 encountered delays.
31 October 1964
UR-700 project cancelled Program: Lunar L3. Launch Vehicle: UR-700. Following the August decree that gave the circumlunar project to Chelomei and the lunar landing project to Korolev, further work on development of the UR-700 by Chelomei was cancelled. However development of the RD-270 engine was continued and Chelomei continued to do UR-700 design studies.
20 October 1965
Draft project work on UR-700/LK-700 approved. Launch Vehicle: UR-700. Ministry of General Machine Building (MOM) Decree 'On approval of work on the draft project of the UR-700/LK-700 lunar complex' was issued.
17 September 1966
Competing lunar landing designs to be evaluated. Launch Vehicle: N1, UR-700. Military-Industrial Commission (VPK) Decree 'On creation of a commission to compare the UR-700-LK-700 and the N1-L3' was issued.
16 November 1966
Government go-ahead for N-1 use in lunar program Program: Lunar L3. Launch Vehicle: N1, UR-700. Mishin's draft plan for the Soviet lunar landing was approved by an expert commission headed by Keldysh. The first N-1 launch was set for March 1968. At same meeting, Chelomei made a last ditch attempt to get his revised UR-700/LK-700 direct landing approach approved in its place. Although Chelomei had lined up the support of Glushko, and Mishin was in a weak position after Korolev's death, Keldysh managed to ensure that the N1-L3 continued. However continued design work on the LK-700, the UR-700 booster, and development of the RD-270 engine were authorised.
21 July 1967
Chelomei signs design documents for UR-700/LK-700 lunar expedition Launch Vehicle: UR-700. Chelomei's TsKBM began work on the UR-700 launch vehicle for manned lunar landing missions in 1962. Chelomei took a sound conservative design approach (i.e. no docking required, no cryogenics).
17 September 1967
LK-700 manned lunar landing spacecraft authorised Launch Vehicle: UR-700. Development of the LK-700 manned lunar landing spacecraft was undertaken in accordance with decree 1070-363 of the Soviet Ministers and Central Committee of the Communist Party on 17 September 1967 and MOM decree 472 of 28 September 1967. Study index number 4855CC by TsNIIMASH in 1966 showed that any development of improved versions of the N1 would be practically equivalent to design and qualification of a new rocket, while the UR-700 modular approach allowed a range of payloads without requalification. The UR-700/LK-700 combination could support the DLB lunar base better, as well as Venus/Mars manned flybys and Mars landing expeditions. Work would continue through the mock-up stage until 1974.
31 December 1970
UR 700/LK-700/RD-270 definitively cancelled. Program: Lunar L3. Launch Vehicle: UR-700. Further development work on the RD-270 engine, UR-700 launch vehicle, and LK-700 lunar landing project are cancelled following the successful Apollo lunar landing.
Bibliography:- 191 - Afanasyev, I B, Neizvestnie korabli, Kosmonavtika, Astronomiya, Znanie, 12-91..
- 288 - Przybilski, Olaf, and Wotzlaw, Stefan, N-1 Herkules - Entwicklung und Absturz einer Traegerrakete, Schriftenreihe der Deutschen Raumfahrtausstellung e.V., 1996.
- 429 - Borisov, A, and Zhuravin, Yu, Novosti kosmonavtiki, "Alternativnaya Luna", No. 9/1999 page 75.
- 443 - Yeteyev, Ivan, Operezhaya vremya, Ocherki, Moscow, 1999..
Back to Index
Last update 12 March 2001.
Contact Mark Wade with any corrections or comments.
Conditions for use of drawings, pictures, or other materials from this site..
© Mark Wade, 2001 .